42 U.S.C. 16441: Funding new interconnection and transmission upgradesText contains those laws in effect through Public Law 119-120 (October 7, 2026).
From Title 42-THE PUBLIC HEALTH AND WELFARECHAPTER 149-NATIONAL ENERGY POLICY AND PROGRAMS
Jump To: Source Credit
§16441. Funding new interconnection and transmission upgrades
The Commission may approve a participant funding plan that allocates costs related to transmission upgrades or new generator interconnection, without regard to whether an applicant is a member of a Commission-approved Transmission Organization, if the plan results in rates that—
(1) are just and reasonable;
(2) are not unduly discriminatory or preferential; and
(3) are otherwise consistent with sections 824d and 824e of title 16.
( Pub. L. 109–58, title XII, § 1242 , Aug. 8, 2005 , 119 Stat. 962 .)