10 USC Subtitle A, PART IV, CHAPTER 169, SUBCHAPTER I: MILITARY CONSTRUCTION
Result 1 of 1
   
 
10 USC Subtitle A, PART IV, CHAPTER 169, SUBCHAPTER I: MILITARY CONSTRUCTION
From Title 10—ARMED FORCESSubtitle A—General Military LawPART IV—SERVICE, SUPPLY, AND PROPERTYCHAPTER 169—MILITARY CONSTRUCTION AND MILITARY FAMILY HOUSING

SUBCHAPTER I—MILITARY CONSTRUCTION

Sec.
2801.
Scope of chapter; definitions.
2802.
Military construction projects.
2803.
Emergency construction.
2804.
Contingency construction.
2805.
Unspecified minor construction.
2806.
Contributions for North Atlantic Treaty Organizations Security Investment.
2807.
Architectural and engineering services and construction design.
2808.
Construction authority in the event of a declaration of war or national emergency.
2809.
Long-term facilities contracts for certain activities and services.
2810.
Military construction projects for innovation, research, development, test, and evaluation.
2811.
Repair of facilities.
2812.
Lease-purchase of facilities.
2813.
Acquisition of existing facilities in lieu of authorized construction.
2814.
Special authority for development of Ford Island, Hawaii.
2815.
Military installation resilience projects.
2815a.
Stormwater management projects for installation and defense access road resilience and waterway and ecosystems conservation.
2816.
Consideration of energy security and energy resilience in life-cycle cost for military construction.
2817.
Authority for certain construction projects in friendly foreign countries.

        

Editorial Notes

Amendments

2023Pub. L. 118–31, div. B, title XXVIII, §2805, Dec. 22, 2023, 137 Stat. 744, added item 2817. Amendment was made pursuant to operation of section 102 of this title.

2022Pub. L. 117–263, div. B, title XXVIII, §2805(b), Dec. 23, 2022, 136 Stat. 2995, added item 2810.

2021Pub. L. 117–81, div. B, §2003(b), title XXVIII, §2803, Dec. 27, 2021, 135 Stat. 2162, 2186, added item 2815a.

Pub. L. 116–283, div. A, title X, §1081(c)(9), div. B, title XXVIII, §2804(b), Jan. 1, 2021, 134 Stat. 3873, 4321, added item 2816 and amended directory language of Pub. L. 116–92, §2801(b)(2). See 2019 Amendment note below.

2019Pub. L. 116–92, div. B, title XXVIII, §2801(b)(2), Dec. 20, 2019, 133 Stat. 1881, as amended by Pub. L. 116–283, div. A, title X, §1081(c)(9), Jan. 1, 2021, 134 Stat. 3873, added item 2815.

2011Pub. L. 112–81, div. A, title X, §1061(23)(B), Dec. 31, 2011, 125 Stat. 1584, struck out item 2815 "Joint use military construction projects: annual evaluation".

2002Pub. L. 107–314, div. A, title III, §313(d)(2), Dec. 2, 2002, 116 Stat. 2508, struck out item 2810 "Construction projects for environmental response actions".

2000Pub. L. 106–398, §1 [div. B, title XXVIII, §2801(b)(2)], Oct. 30, 2000, 114 Stat. 1654, 1654A-412, added item 2815.

1999Pub. L. 106–65, div. B, title XXVIII, §2802(a)(2), Oct. 5, 1999, 113 Stat. 848, added item 2814.

1996Pub. L. 104–201, div. B, title XXVIII, §2802(c)(2), Sept. 23, 1996, 110 Stat. 2787, substituted "Organizations Security Investment" for "Organization Infrastructure" in item 2806.

Pub. L. 104–106, div. A, title XV, §1503(a)(31), Feb. 10, 1996, 110 Stat. 512, inserted period at end of item 2811.

1994Pub. L. 103–337, div. B, title XXVIII, §2801(b), Oct. 5, 1994, 108 Stat. 3050, substituted "Repair" for "Renovation" in item 2811.

1993Pub. L. 103–160, div. B, title XXVIII, §2805(a)(2), Nov. 30, 1993, 107 Stat. 1887, added item 2813.

1991Pub. L. 102–190, div. B, title XXVIII, §2805(a)(2), Dec. 5, 1991, 105 Stat. 1538, substituted "Long-term facilities contracts for certain activities and services" for "Test of long-term facilities contracts" in item 2809.

1989Pub. L. 101–189, div. B, title XXVIII, §2809(b), Nov. 29, 1989, 103 Stat. 1650, added item 2812.

1987Pub. L. 100–26, §7(e)(3), Apr. 21, 1987, 101 Stat. 281, redesignated item 2810 "Renovation of facilities" as item 2811.

1986Pub. L. 99–661, div. A, title III, §315(b), Nov. 14, 1986, 100 Stat. 3854, added item 2810 "Renovation of facilities".

Pub. L. 99–499, title II, §211(b)(2), Oct. 17, 1986, 100 Stat. 1726, added item 2810 "Construction projects for environmental response actions".

1985Pub. L. 99–167, title VIII, §811(b), Dec. 3, 1985, 99 Stat. 991, added item 2809.

§2801. Scope of chapter; definitions

(a) The term "military construction" as used in this chapter or any other provision of law includes any construction, development, conversion, or extension of any kind carried out with respect to a military installation, whether to satisfy temporary or permanent requirements, or any acquisition of land or construction of a defense access road (as described in section 210 of title 23).

(b) A military construction project includes all military construction work, or any contribution authorized by this chapter, necessary to produce a complete and usable facility or a complete and usable improvement to an existing facility (or to produce such portion of a complete and usable facility or improvement as is specifically authorized by law).

(c) In this chapter and chapter 173 of this title:

(1) The term "appropriate committees of Congress" means the congressional defense committees and, with respect to any project to be carried out by, or for the use of, an intelligence component of the Department of Defense, the Permanent Select Committee on Intelligence of the House of Representatives and the Select Committee on Intelligence of the Senate.

(2) The term "facility" means a building, structure, or other improvement to real property.

(3) The term "life-cycle cost-effective", with respect to a project, product, or measure, means that the sum of the present values of investment costs, capital costs, installation costs, energy costs, operating costs, maintenance costs, and replacement costs, as estimated for the lifetime of the project, product, or measure, does not exceed the base case (current or standard) for the practice, product, or measure.

(4) The term "military installation" means a base, camp, post, station, yard, center, or other activity under the jurisdiction of the Secretary of a military department or, in the case of an activity in a foreign country, under the operational control of the Secretary of a military department or the Secretary of Defense, without regard to the duration of operational control.

(5) The term "Secretary concerned" includes the Secretary of Defense with respect to matters concerning the Defense Agencies.


(d) This chapter (other than sections 2830,1 2835, and 2836 of this chapter) does not apply to the Coast Guard or to civil works projects of the Army Corps of Engineers.

(Added Pub. L. 97–214, §2(a), July 12, 1982, 96 Stat. 153; amended Pub. L. 100–26, §7(k)(2), Apr. 21, 1987, 101 Stat. 284; Pub. L. 100–180, div. A, title VI, §632(b)(1), title XII, §1231(15), div. B, subdiv. 3, title I, §2306(b), Dec. 4, 1987, 101 Stat. 1105, 1160, 1216; Pub. L. 102–484, div. A, title X, §1052(37), Oct. 23, 1992, 106 Stat. 2501; Pub. L. 102–496, title IV, §403(b), Oct. 24, 1992, 106 Stat. 3185; Pub. L. 104–106, div. A, title XV, §1502(a)(10), Feb. 10, 1996, 110 Stat. 503; Pub. L. 106–65, div. A, title X, §1067(1), Oct. 5, 1999, 113 Stat. 774; Pub. L. 108–136, div. A, title X, §1043(b)(16), div. B, title XXVIII, §2801, Nov. 24, 2003, 117 Stat. 1611, 1719; Pub. L. 109–163, div. A, title X, §1056(c)(9), Jan. 6, 2006, 119 Stat. 3440; Pub. L. 109–364, div. B, title XXVIII, §2851(b)(4), Oct. 17, 2006, 120 Stat. 2495; Pub. L. 110–181, div. B, title XXVIII, §2802(b), Jan. 28, 2008, 122 Stat. 539; Pub. L. 110–417, div. B, title XXVIII, §2801(a), Oct. 14, 2008, 122 Stat. 4719.)


Editorial Notes

References in Text

Section 2830 of this chapter, referred to in subsec. (d), was repealed by Pub. L. 116–283, div. B, title XXVIII, §2812(a), Jan. 1, 2021, 134 Stat. 4326.

Amendments

2008—Subsec. (a). Pub. L. 110–181 inserted ", or any acquisition of land or construction of a defense access road (as described in section 210 of title 23)" before period at end.

Subsec. (c). Pub. L. 110–417 added par. (3) and redesignated former pars. (4), (1), (2), and (3) as (1), (2), (4), and (5), respectively.

2006—Subsec. (c). Pub. L. 109–364 inserted "and chapter 173 of this title" after "this chapter" in introductory provisions.

Subsec. (d). Pub. L. 109–163 substituted "sections 2830, 2835, and 2836 of this chapter" for "sections 2830 and 2835".

2003—Subsec. (a). Pub. L. 108–136, §2801(a), inserted before period at end ", whether to satisfy temporary or permanent requirements".

Subsec. (c)(2). Pub. L. 108–136, §2801(b), inserted before period at end ", without regard to the duration of operational control".

Subsec. (c)(4). Pub. L. 108–136, §1043(b)(16), substituted "the congressional defense committees" for "the Committee on Armed Services and the Committee on Appropriations of the Senate and the Committee on Armed Services and the Committee on Appropriations of the House of Representatives".

1999—Subsec. (c)(4). Pub. L. 106–65 substituted "and the Committee on Armed Services" for "and the Committee on National Security".

1996—Subsec. (c)(4). Pub. L. 104–106 substituted "the Committee on Armed Services and the Committee on Appropriations of the Senate and the Committee on National Security and the Committee on Appropriations of the" for "the Committees on Armed Services and on Appropriations of the Senate and".

1992—Subsec. (c)(4). Pub. L. 102–496 inserted before period at end "and, with respect to any project to be carried out by, or for the use of, an intelligence component of the Department of Defense, the Permanent Select Committee on Intelligence of the House of Representatives and the Select Committee on Intelligence of the Senate".

Subsec. (d). Pub. L. 102–484 substituted "sections 2830 and 2835" for "sections 2828(g) and 2830".

1987—Subsec. (c). Pub. L. 100–26 inserted "The term" after each par. designation and struck out uppercase letter of first word after first quotation marks in pars. (1), (2), and (4) and substituted lowercase letter.

Subsec. (c)(3). Pub. L. 100–180, §1231(15), substituted "Defense Agencies" for "defense agencies".

Subsec. (d). Pub. L. 100–180, §2306(b), substituted "(other than sections 2828(g) and 2830)" for "(other than section 2830)".

Pub. L. 100–180, §632(b)(1), inserted "(other than section 2830)" after "This chapter".


Statutory Notes and Related Subsidiaries

Effective Date

Pub. L. 97–214, §12, July 12, 1982, 96 Stat. 176, provided:

"(a) Except as provided in subsection (b), the amendments made by this Act [see Short Title of 1982 Amendment note below] shall take effect on October 1, 1982, and shall apply to military construction projects, and to construction and acquisition of military family housing, authorized before, on, or after such date.

"(b) The amendment made by section 4 [amending section 138(f)(1) [now 114(b)] of this title] shall apply with respect to funds appropriated for fiscal years beginning after September 30, 1983."

Short Title of 1982 Amendment

Pub. L. 97–214, §1, July 12, 1982, 96 Stat. 153, provided that: "This Act [see Tables for classification] may be cited as the 'Military Construction Codification Act'."

Transfer of Functions

For transfer of authorities, functions, personnel, and assets of the Coast Guard, including the authorities and functions of the Secretary of Transportation relating thereto, to the Department of Homeland Security, and for treatment of related references, see sections 468(b), 551(d), 552(d), and 557 of Title 6, Domestic Security, and the Department of Homeland Security Reorganization Plan of November 25, 2002, as modified, set out as a note under section 542 of Title 6.

Plan and Report on Critical Infrastructure Systems at Military Installations

Pub. L. 118–31, div. B, title XXVIII, §2853, Dec. 22, 2023, 137 Stat. 763, provided that:

"(a) Plan.—Not later than one year after the date of the enactment of this Act [Dec. 22, 2023], the Secretary of Defense, in coordination with each Secretary of a military department, shall submit to the Committees on Armed Services of the Senate and the House of Representatives a plan to implement a standardized system to measure and report on the condition and performance of, the level of investment in, and any applicable risks to critical infrastructure systems owned by the Federal Government that—

"(1) have not been privatized or transferred pursuant to a conveyance under section 2688 of title 10, United States Code; and

"(2) are located on a military installation (as defined in section 2801 of such title).

"(b) Report.—

"(1) In general.—Beginning on February 1 of the year immediately following the date on which the plan under subsection (a) is submitted, and annually thereafter, the Secretary of Defense, in coordination with each Secretary of a military department, shall submit to the Committees on Armed Services of the Senate and the House of Representatives a consolidated report on the condition of critical infrastructure systems owned by the Federal Government located at military installations.

"(2) Elements.—Each report required by paragraph (1) shall include the following:

"(A) Installation-level data for each critical infrastructure system described in paragraph (1) that includes the following for each such system:

"(i) For the five-year period preceding the date of submission of the report, all instances of noncompliance of such system with any applicable Federal or State law or regulation, including information on any prior or current consent order or equivalent compliance agreement with any Federal or State regulatory agency.

"(ii) The year of original installation of critical infrastructure system components, including treatment facilities, pump stations, and storage tanks.

"(iii) The average age of distribution system piping and wiring.

"(iv) The rate of system recapitalization, represented as an annual percentage replacement rate of all critical infrastructure system assets.

"(v) For the one-year period preceding the date of submission of the report, the percentage of key system operational components (including fire hydrants, valves, and backflow preventors) inspected and determined through testing to be fully operational.

"(vi) For the one-year period preceding the date of submission of the report, the absolute number, and a normalized measure for comparative purposes, of all unplanned system outages.

"(vii) For the one-year period preceding the date of submission of the report, the absolute duration, and a normalized measure for comparative purposes, of all unplanned system outages.

"(viii) For the one-year period preceding the date of submission of the report, the absolute number, and a normalized measure for comparative purposes, of all critical infrastructure system main breaks and leaks.

"(B) A standardized risk assessment for each military installation, identifying the current and projected level of risk related to the following:

"(i) The ability to maintain compliance with applicable current and proposed State regulations and standards and applicable regulations and policies of the Department of Defense and the military departments related to each critical infrastructure system described in paragraph (1), and the ability to operate critical infrastructure systems in accordance with accepted industry standards.

"(ii) The ability to maintain a consistent and compliant supply of water for current and projected future installation needs based on current and projected source water availability and quality, including an assessment of source water contamination risks for each critical infrastructure system described in paragraph (1).

"(iii) The ability of each critical infrastructure system described in paragraph (1) to withstand severe weather events, including drought, flooding, and temperature fluctuations.

"(iv) The ability for utility industrial controls systems for each critical infrastructure system described in paragraph (1) to maintain compliance with applicable current and proposed cybersecurity standards and regulations.

"(3) Form.—A report under this subsection shall be submitted in an unclassified form but may contain a classified annex.

"(c) Critical Infrastructure System Defined.—In this section, the term 'critical infrastructure system' includes a transportation infrastructure system and a utilities infrastructure system."

Pilot Program To Support Combatant Command Military Construction Priorities

Pub. L. 116–283, div. B, title XXVIII, §2863, Jan. 1, 2021, 134 Stat. 4358, provided that:

"(a) Pilot Program.—The Secretary of Defense shall conduct a pilot program to evaluate the usefulness of reserving a portion of the military construction funds of the military departments to help the combatant commands satisfy their military construction priorities in a timely manner.

"(b) Location.—The Secretary of Defense shall conduct the pilot program for the benefit of the United States Indo-Pacific Command in the area of responsibility of the United States Indo-Pacific Command.

"(c) Required Investment.—For each fiscal year during which the pilot program is conducted, the Secretary of Defense shall reserve to carry out military construction projects under the pilot program an amount equal to 10 percent of the total amount authorized to be appropriated for military construction projects by titles XXI, XXII, and XXIII of the Military Construction Authorization Act for that fiscal year.

"(d) Commencement and Duration.—

"(1) Commencement.—The Secretary of Defense shall commence the pilot program no later than October 1, 2023. The Secretary may commence the pilot program as early as October 1, 2022, if the Secretary determines that compliance with the reservation of funds requirement under subsection (c) is practicable beginning with fiscal year 2023.

"(2) Duration.—The pilot program shall be in effect for the fiscal year in which the Secretary commences the pilot program, as described in paragraph (1), and the subsequent two fiscal years. Any construction commenced under the pilot program before the expiration date may continue to completion.

"(e) Progress Report.—Not later than February 15 of the final fiscal year of the pilot program, the Secretary of Defense shall submit to the congressional defense committees [Committees on Armed Services and Appropriations of the Senate and the House of Representatives] a report evaluating the success of the pilot program in improving the timeliness of the United States Indo-Pacific Command in achieving its military construction priorities. The Secretary shall include in the report—

"(1) an evaluation of the likely positive and negative impacts were the pilot program extended or made permanent and, if extended or made permanent, the likely positive and negative impacts of expansion to cover all or additional combatant commands; and

"(2) the recommendations of the Secretary regarding whether the pilot program should be extended or made permanent and expanded."

Permitting Machine Room-Less Elevators in Department of Defense Facilities

Pub. L. 115–91, div. B, title XXVIII, §2875, Dec. 12, 2017, 131 Stat. 1871, provided that:

"(a) In General.—The Secretary of Defense shall issue modifications to all relevant construction and facilities specifications to ensure that machine room-less elevators (MRLs) are not prohibited in buildings and facilities throughout the Department of Defense, including modifications to the Unified Facilities Guide Specifications (UFGS), the Naval Facilities Engineering Command Interim Technical Guidance, and the Army Corps of Engineers Engineering and Construction Bulletin.

"(b) Conforming to Best Practices.—In addition to the modifications required under subsection (a), the Secretary may issue further modifications to conform generally with commercial best practices as reflected in the safety code for elevators and escalators as issued by the American Society of Mechanical Engineers.

"(c) Deadlines.—The Secretary shall promulgate interim MRL standards not later than 180 days after the date of the enactment of this Act [Dec. 12, 2017], and shall issue final and formal MRL specifications not later than 1 year after the date of the enactment of this Act.

"(d) Report.—Not later than 1 year after the date of the enactment of this Act, the Secretary shall issue a report to the congressional defense committees [Committees on Armed Services and Appropriations of the Senate and the House of Representatives] on the integration and utilization of MRLs, including information on quantity, location, problems, and successes."

1 See References in Text note below.

§2802. Military construction projects

(a) The Secretary of Defense and the Secretaries of the military departments may carry out such military construction projects, land acquisitions, and defense access road projects (as described under section 210 of title 23) as are authorized by law.

(b) Authority provided by law to carry out a military construction project includes authority for—

(1) surveys and site preparation;

(2) acquisition, conversion, rehabilitation, and installation of facilities;

(3) acquisition and installation of equipment and appurtenances integral to the project;

(4) acquisition and installation of supporting facilities (including utilities) and appurtenances incident to the project; and

(5) planning, supervision, administration, and overhead incident to the project.


(c) In determining the scope of a proposed military construction project, the Secretary concerned shall submit to the President such recommendations as the Secretary considers to be appropriate regarding the incorporation and inclusion of life-cycle cost-effective practices as an element in the project documents submitted to Congress in connection with the budget submitted pursuant to section 1105 of title 31 for the fiscal year in which a contract is proposed to be awarded for the project.

[(d) Repealed. Pub. L. 114–328, div. B, title XXVIII, §2811(b), Dec. 23, 2016, 130 Stat. 2716.]

(e)(1) If a construction project, land acquisition, or defense access road project described in paragraph (2) will be carried out pursuant to a provision of law other than a Military Construction Authorization Act, the Secretary concerned shall—

(A) comply with the congressional notification requirement contained in the provision of law under which the construction project, land acquisition, or defense access road project will be carried out and submit to the congressional defense committees any materials required to be submitted to Congress or any other congressional committees pursuant to the congressional notification requirement; or

(B) in the absence of such a congressional notification requirement, submit to the congressional defense committees, in an electronic medium pursuant to section 480 of this title, a report describing the construction project, land acquisition, or defense access road project at least 15 days before commencing the construction project, land acquisition, or defense access road project.


(2) Except as provided in paragraph (3), a construction project, land acquisition, or defense access road project subject to the notification requirement imposed by paragraph (1) is a construction project, land acquisition, or defense access road project that—

(A) is not specifically authorized in a Military Construction Authorization Act;

(B) will be carried out by a military department, Defense Agency, or Department of Defense Field Activity; and

(C) will be located on a military installation.


(3) This subsection does not apply to a construction project, land acquisition, or defense access road project described in paragraph (2) whose cost is less than or equal to the threshold amount specified in section 2805(b) of this title.

(f)(1) In addition to any other applicable consultation requirement pursuant to law or Department of Defense policy, if a proposed military construction project is likely to significantly impact tribal lands, known sacred sites, or tribal treaty rights, the Secretary concerned shall initiate consultation with the tribal government of each impacted Indian tribe—

(A) to determine the nature and extent of such impact;

(B) to determine whether such impact can be avoided or mitigated in the design and implementation of the project; and

(C) if such impact cannot be avoided, to develop feasible measures consistent with applicable law to mitigate the impact and estimate the cost of the mitigation measures.


(2) As part of the Department of Defense Form 1391 submitted to the appropriate committees of Congress for a military construction project covered by paragraph (1), the Secretary concerned, to the extent possible at the time of such submission, shall include a description of the current status of the consultation conducted under such paragraph and specifically address each of the items specified in subparagraphs (A), (B), and (C) of such paragraph.

(3) The requirement under paragraph (1) does not affect the obligation of the Secretary concerned to comply with any other applicable consultation requirement pursuant to law or Department of Defense policy.

(4) In this subsection:

(A) The term "Indian tribe" has the meaning given that term in section 4 of the Indian Self-Determination and Education Assistance Act (25 U.S.C. 5304).

(B) The term "tribal government" means the recognized governing body of an Indian tribe.

(C) The term "sacred site" has the meaning given that term in Executive Order No. 13007, as in effect on the date of the enactment of the National Defense Authorization Act for Fiscal Year 2020.

(Added Pub. L. 97–214, §2(a), July 12, 1982, 96 Stat. 154; amended Pub. L. 110–181, div. B, title XXVIII, §2802(a), Jan. 28, 2008, 122 Stat. 539; Pub. L. 110–417, div. B, title XXVIII, §2801(b), Oct. 14, 2008, 122 Stat. 4719; Pub. L. 113–66, div. B, title XXVIII, §2807(c), Dec. 26, 2013, 127 Stat. 1012; Pub. L. 113–291, div. B, title XXVIII, §§2801, 2803(b), Dec. 19, 2014, 128 Stat. 3695, 3697; Pub. L. 114–328, div. B, title XXVIII, §2811(b), (c), Dec. 23, 2016, 130 Stat. 2716; Pub. L. 115–91, div. A, title X, §1081(d)(15), Dec. 12, 2017, 131 Stat. 1600; Pub. L. 115–232, div. B, title XXVIII, §2803, Aug. 13, 2018, 132 Stat. 2261; Pub. L. 116–92, div. A, title XVII, §1731(a)(53), div. B, title XXVIII, §2802, Dec. 20, 2019, 133 Stat. 1815, 1881.)


Editorial Notes

References in Text

Executive Order No. 13007, referred to in subsec. (f)(4)(C), is Ex. Ord. No. 13007, May 24, 1996, 61 F.R. 26771, which is set out as a note under section 1996 of Title 42, The Public Health and Welfare.

The date of the enactment of the National Defense Authorization Act for Fiscal Year 2020, referred to in subsec. (f)(4)(C), is the date of enactment of Pub. L. 116–92, which was approved Dec. 20, 2019.

Amendments

2019—Subsec. (e)(1). Pub. L. 116–92, §1731(a)(53), substituted "shall—" for "shall" and inserted subpar. (A) designation before "comply with the congressional notification requirement".

Subsec. (f). Pub. L. 116–92, §2802, added subsec. (f).

2018—Subsec. (e)(1). Pub. L. 115–232 substituted "Secretary concerned shall" for "Secretary concerned shall—", struck out subpar. (A) designation before "comply with the congressional notification requirement", and inserted "and submit to the congressional defense committees any materials required to be submitted to Congress or any other congressional committees pursuant to the congressional notification requirement" after "road project will be carried out".

2017—Subsec. (d). Pub. L. 115–91, §1081(d)(15), amended Pub. L. 114–328, §2811(c). See 2016 Amendment note below.

2016—Subsec. (d). Pub. L. 114–328, §2811(b), struck out subsec. (d) which related to requirements for military construction projects funded through payments-in-kind or in-kind contributions, inclusion of such projects in budget justification documents, and exceptions to those requirements.

Pub. L. 114–328, §2811(c), as amended by Pub. L. 115–91, §1081(d)(15), repealed Pub. L. 113–291, §2803(b). See 2014 Amendment note below.

2014—Subsec. (d). Pub. L. 113–291, §2803(b), which substituted "payments-in-kind or in-kind contributions" for "payment-in-kind contributions" in par. (1), added par. (3) and struck out former par. (3) which described certain military construction projects to which subsec. (d) did not apply, and substituted "paragraph (3), by reference to section 2687a(f)(4)(D) of this title," for "paragraph (3)(C)" in par. (4), was repealed by Pub. L. 114–328, §2811(c), as amended by Pub. L. 115–91, §1081(d)(15).

Subsec. (e). Pub. L. 113–291, §2801, added subsec. (e).

2013—Subsec. (d). Pub. L. 113–66 added subsec. (d).

2008—Subsec. (a). Pub. L. 110–181 inserted ", land acquisitions, and defense access road projects (as described under section 210 of title 23)" after "military construction projects".

Subsec. (c). Pub. L. 110–417 added subsec. (c).


Statutory Notes and Related Subsidiaries

Effective Date of 2017 Amendment

Pub. L. 115–91, div. A, title X, §1081(d), Dec. 12, 2017, 131 Stat. 1599, provided that the amendment made by section 1081(d)(15) is effective as of Dec. 23, 2016, and as if included in Pub. L. 114–328 as enacted.

Effective Date

For effective date and applicability of section, see section 12(a) of Pub. L. 97–214, set out as a note under section 2801 of this title.

Inclusion on Department of Defense Form 1391 of Information on Consideration of Certain Methods of Construction for Certain Military Construction Projects

Pub. L. 118–31, div. B, title XXVIII, §2808, Dec. 22, 2023, 137 Stat. 746, provided that:

"(a) In General.—As part of the Department of Defense Form 1391 submitted to the appropriate committees of Congress for a covered military construction project, each covered official shall, to the extent practicable, include information on whether all relevant construction materials and methods of construction included in the Unified Facilities Criteria/DoD Building Code (UFC 1–200–01) were considered in the design of such covered military construction project.

"(b) Definitions.—In this section:

"(1) The terms 'appropriate committees of Congress' and 'military construction project' have the meanings given in section 2801 of title 10, United States Code.

"(2) The term 'covered military construction project' means a military construction project with an estimated total cost in excess of $9,000,000.

"(3) The term 'covered official' means—

"(A) the Secretary of Defense; and

"(B) each Secretary of a military department."

Inclusion of Military Installation Resilience in Real Property Management and Installation Master Planning of Department

Pub. L. 118–31, div. B, title XXVIII, §2857, Dec. 22, 2023, 137 Stat. 767, provided that:

"(a) [sic; there is no subsec. (b)] In General.—Not later than one year after the date of the enactment of this Act [Dec. 22, 2023], the Secretary of Defense shall—

"(1) update Department of Defense Instruction 4165.70 (relating to real property management) and Unified Facilities Criteria 2–100–01 (relating to installation master planning) to—

"(A) include a requirement to incorporate the impact of military installation resilience in all installation master plans;

"(B) include a list of all sources of information approved by the Department of Defense;

"(C) define the 17 identified military installation resilience hazards to ensure that the impacts from such hazards are reported consistently across the Department;

"(D) require each commander of a military installation to address the rationale for determining that any such hazard is not applicable to the military installation concerned;

"(E) standardize reporting formats for military installation resilience plans;

"(F) establish and define standardized risk rating categories for the use by each Secretary of a military department; and

"(G) define criteria for determining the level of risk to a military installation to compare hazards between military departments; and

"(2) require each Secretary of a military department to update the handbook for the military department concerned to incorporate the requirements under paragraph (1)."

Consideration of Installation of Integrated Solar Roofing To Improve Energy Resiliency of Military Installations

Pub. L. 117–263, div. B, title XXVIII, §2810, Dec. 23, 2022, 136 Stat. 2997, provided that: "The Secretary of Defense shall amend the Unified Facilities Criteria/DoD Building Code (UFC 1–200–01) to require that planning and design for military construction projects inside the United States include consideration of the feasibility and cost-effectiveness of installing integrated solar roofing as part of the project, for the purpose of—

"(1) promoting on-installation energy security and energy resilience;

"(2) providing grid support to avoid energy disruptions; and

"(3) facilitating implementation and greater use of the authority provided by subsection (h) of section 2911 of title 10, United States Code."

Revision of Unified Facilities Guide Specifications and Unified Facilities Criteria To Include Specifications on Use of Gas Insulated Switchgear and Criteria and Specifications on Microgrids and Microgrid Converters

Pub. L. 117–263, div. B, title XXVIII, §2811, Dec. 23, 2022, 136 Stat. 2997, provided that:

"(a) Gas Insulated Switchgear.—Not later than one year after the date of the enactment of this Act [Dec. 23, 2022], the Under Secretary of Defense for Acquisition and Sustainment shall modify the Unified Facilities Guide Specifications to include a distinct specification for medium voltage gas insulated switchgear.

"(b) Microgrids.—Not later than one year after the date of the enactment of this Act, the Under Secretary of Defense for Acquisition and Sustainment shall—

"(1) modify the Unified Facilities Criteria to include criteria for microgrids; and

"(2) modify the Unified Facilities Guide Specifications to include specifications for microgrids and microgrid controllers."

Determination and Notification Relating to Executive Orders That Impact Cost and Scope of Work of Military Construction Projects

Pub. L. 117–263, div. B, title XXVIII, §2812, Dec. 23, 2022, 136 Stat. 2997, provided that:

"(a) Determination and Update of Form 1391.—Not later than 30 days after the date on which an Executive order is signed by the President, the Secretary concerned shall—

"(1) determine whether implementation of the Executive order would cause a cost or scope of work variation for a military construction project under the jurisdiction of the Secretary concerned;

"(2) assess the potential for life-cycle cost savings associated with implementation of the Executive order for such a project; and

"(3) update the Department of Defense Form 1391 for each such project that has not been submitted for congressional consideration, where such implementation would affect such cost or scope of work variation, including—

"(A) projects to be commenced in the next fiscal year beginning after the date on which the Executive order was signed; and

"(B) projects covered by the future-years defense program submitted under section 221 of title 10, United States Code.

"(b) Notification to Congress.—Not later than 10 days after determining under subsection (a)(1) that implementation of an Executive order would cause a cost or scope of work variation for a military construction project, the Secretary concerned shall submit to the congressional defense committees [Committees on Armed Services and Appropriations of the Senate and the House of Representatives] a report indicating the estimated cost increases, scope of work increases, life-cycle costs, and any other impacts of such implementation.

"(c) Certification.—Along with the submission to Congress of the budget of the President for a fiscal year under section 1105(a) of title 31, United States Code, each Secretary concerned shall certify to Congress that each Department of Defense Form 1391 provided to Congress for that fiscal year for a military construction project has been updated with any cost or scope of work variation specified in subsection (a)(1) with respect to an Executive order signed during the four-year period preceding such certification, including an indication of any cost increases for such project that is directly attributable to such Executive order.

"(d) Secretary Concerned Defined.—In this section, the term 'Secretary concerned' has the meaning given that term in section 101 of title 10, United States Code."

Requirement for Inclusion of Department of Defense Forms 1391 With Annual Budget Submission by President

Pub. L. 117–263, div. B, title XXVIII, §2813, Dec. 23, 2022, 136 Stat. 2998, provided that: "Concurrently with the submission to Congress by the President of the annual budget of the Department of Defense for a fiscal year under section 1105(a) of title 31, United States Code, the President shall include each Department of Defense Form 1391, or successor similar form, for a military construction project to be carried out during that fiscal year."

Electrical Charging Capability Construction Requirements Relating to Parking for Federal Government Motor Vehicles

Pub. L. 117–263, div. B, title XXVIII, §2875, Dec. 23, 2022, 136 Stat. 3014, provided that:

"(a) In General.—If the Secretary concerned develops plans for a project to construct any facility that includes or will include parking for covered motor vehicles, the Secretary concerned shall include in any Department of Defense Form 1391, or successor form, submitted to Congress for that project—

"(1) the provision of electric vehicle charging capability at the facility adequate to provide electrical charging, concurrently, for not less than 15 percent of all covered motor vehicles planned to be parked at the facility;

"(2) the inclusion of the cost of constructing such capability in the overall cost of the project; and

"(3) an analysis of whether a parking structure or lot will be the primary charging area for covered motor vehicles or if another area, such as public works or the motor pool, will be the primary charging area.

"(b) Definitions.—In this section:

"(1) The term 'covered motor vehicle' means a Federal Government motor vehicle, including a motor vehicle leased by the Federal Government.

"(2) The term 'Secretary concerned' means—

"(A) the Secretary of a military department with respect to facilities under the jurisdiction of that Secretary; and

"(B) the Secretary of Defense with respect to matters concerning the Defense Agencies and facilities of a reserve component owned by a State rather than the United States."

Amendment of Unified Facilities Criteria To Require Inclusion of Private Nursing and Lactation Space in Certain Military Construction Projects

Pub. L. 117–81, div. B, title XXVIII, §2841, Dec. 27, 2021, 135 Stat. 2201, provided that:

"(a) Amendment Required.—The Secretary of Defense shall amend UFC 1–4.2 (Nursing and Lactation Rooms) of the Unified Facilities Criteria/DoD Building Code (UFC 1–200–01) to require that military construction planning and design for buildings likely to be regularly frequented by nursing mothers who are members of the uniformed services, civilian employees of the Department of Defense, contractor personnel, or visitors include a private nursing and lactation room or other private space suitable for that purpose.

"(b) Deadline.—The Secretary of Defense shall complete the amendment process required by subsection (a) and implement the amended UFC 1–4.2 not later than one year after the date of the enactment of this Act [Dec. 27, 2021]."

Revisions to Unified Facilities Criteria Regarding Use of Variable Refrigerant Flow Systems

Pub. L. 117–81, div. B, title XXVIII, §2842, Dec. 27, 2021, 135 Stat. 2201, provided that:

"(a) Publication and Comment Period Requirements.—The Under Secretary of Defense for Acquisition and Sustainment shall publish any proposed revisions to the Unified Facilities Criteria regarding the use of variable refrigerant flow systems in the Federal Register and shall specify a comment period of at least 60 days.

"(b) Notice and Justification Requirements.—The Secretary of Defense shall submit to the Committees on Armed Services of the Senate and the House of Representatives a written notice and justification for any proposed revisions to the Unified Facilities Criteria regarding the use of variable refrigerant flow systems not later than 30 days after the date of publication in the Federal Register."

Amendment of Unified Facilities Criteria To Promote Energy Efficient Military Installations

Pub. L. 117–81, div. B, title XXVIII, §2843, Dec. 27, 2021, 135 Stat. 2202, provided that:

"(a) Unified Facilities Criteria Amendment Required.—To the extent practicable, the Secretary of Defense shall amend the Unified Facilities Criteria relating to military construction planning and design to ensure that building practices and standards of the Department of Defense incorporate the latest consensus-based codes and standards for energy efficiency and conservation, including the 2021 International Energy Conservation Code and the ASHRAE Standard 90.1-2019.

"(b) Implementation of Amendment.—The Secretary of Defense shall complete the amendment process required by subsection (a) in a timely manner so that any Department of Defense Form 1391 submitted to Congress in connection with the budget submission for fiscal year 2024 and thereafter complies with the Unified Facilities Criteria, as amended pursuant to such subsection.

"(c) Reporting Requirement.—Not later than February 1, 2024, the Secretary of Defense shall submit to the Committees on Armed Services of the House of Representatives and the Senate a report—

"(1) describing the extent to which the Unified Facilities Criteria, as amended pursuant to subsection (a), incorporate the latest consensus-based codes and standards for energy efficiency and conservation, including the 2021 International Energy Conservation Code and the ASHRAE Standard 90.1-2019, as required by such subsection; and

"(2) in the case of any instance in which the Unified Facilities Criteria continues to deviate from such consensus-based codes and standards for energy efficiency and conservation, identifying the deviation and explaining the reasons for the deviation."

Additional Department of Defense Activities To Improve Energy Resiliency of Military Installations

Pub. L. 117–81, div. B, title XXVIII, §2844, Dec. 27, 2021, 135 Stat. 2202, provided that:

"(a) Consideration of Including Energy Microgrid in Military Construction Projects.—

"(1) Amendment of unified facilities criteria required.—The Secretary of Defense shall amend the Unified Facilities Criteria/DoD Building Code (UFC 1–200–01) to require that planning and design for military construction projects inside the United States include consideration of the feasibility and cost-effectiveness of installing an energy microgrid as part of the project, including intentional islanding capability of at least seven consecutive days, for the purpose of—

"(A) promoting on-installation energy security and energy resilience; and

"(B) facilitating implementation and greater use of the authority provided by subsection (h) of section 2911 of title 10, United States Code, as added and amended by section 2825 of the Military Construction Authorization Act for Fiscal Year 2021 (division B of Public Law 116–283).

"(2) Deadline.—The Secretary of Defense shall complete the amendment process required by paragraph (1) and implement the amendment not later than September 1, 2022.

"(b) Contracts for Emergency Access to Existing On-installation Renewable Energy Sources.—In the case of a covered renewable energy generating source located on a military installation pursuant to a lease of non-excess defense property under section 2667 of title 10, United States Code, the Secretary of the military department concerned is encouraged to negotiate with the owner and operator of the renewable energy generating source to revise the lease contract to permit the military installation to access the renewable energy generating source during an emergency. The negotiations shall include consideration of the ease of modifying the renewable energy generating source to include an islanding capability, the necessity of additional infrastructure to tie the renewable energy generating source into the installation energy grid, and the cost of such modifications and infrastructure.

"(c) Definitions.—In this section:

"(1) The term 'covered renewable energy generating source' means a renewable energy generating source that, on the date of the enactment of this Act [Dec. 27, 2021]—

"(A) is located on a military installation inside the United States; but

"(B) cannot be used as a direct source of resilient energy for the installation in the event of a power disruption.

"(2) The term 'islanding capability' refers to the ability to remove an energy system, such as a microgrid, from the local utility grid and to operate the energy system, at least temporarily, as an integrated, stand-alone system, during an emergency involving the loss of external electric power supply.

"(3) The term 'microgrid' means an integrated energy system consisting of interconnected loads and energy resources with an islanding capability to permit functioning separate from the local utility grid."

Pilot Program on Increased Use of Sustainable Building Materials in Military Construction

Pub. L. 117–81, div. B, title XXVIII, §2861, Dec. 27, 2021, 135 Stat. 2212, as amended by Pub. L. 117–263, div. B, title XXVIII, §2865, Dec. 23, 2022, 136 Stat. 3011; Pub. L. 118–31, div. B, title XXVIII, §2871, Dec. 22, 2023, 137 Stat. 775, provided that:

"(a) Pilot Program Required.—Each Secretary of a military department shall conduct a pilot program to evaluate the effect that the use of sustainable building materials as the primary construction material in military construction may have on the environmental sustainability, infrastructure resilience, cost effectiveness, and construction timeliness of military construction.

"(b) Project Selection and Locations.—

"(1) Minimum number of projects.—Each Secretary of a military department shall carry out, under the pilot program, at least—

"(A) one military construction project for mass timber; and

"(B) one military construction project for low carbon concrete.

"(2) Project locations.—The pilot program shall be conducted at military installations in the United States—

"(A) that are identified as vulnerable to extreme weather events; and—

"(B) for which a military construction project is authorized but a request for proposal has not been released.

"(c) Inclusion of Military Unaccompanied Housing Project.—The Secretaries of the military departments shall coordinate the selection of military construction projects to be carried out under the pilot program so that at least one of the military construction projects involves construction of military unaccompanied housing.

"(d) Duration of Program.—The authority of the Secretary of a military department to carry out a military construction project under the pilot program shall expire on September 30, 2025. Any construction commenced under the pilot program before the expiration date may continue to completion.

"(e) Deadline for Commencement of Construction.—Any construction pursuant to a military construction project carried out under the pilot program must commence by not later than January 1, 2025.

"(f) Reporting Requirement.—

"(1) Report required.—Not later than 180 days after the date of the enactment of this Act [Dec. 27, 2021], and every 180 days thereafter through December 31, 2025, the Secretaries of the military departments shall submit to the congressional defense committees [Committee on Armed Services and Committee on Appropriations of the Senate and House of Representatives] a report on the progress of the pilot program.

"(2) Report elements.—The report shall include the following:

"(A) A description of the status of the military construction projects selected to be conducted under the pilot program.

"(B) An explanation of the reasons why those military construction projects were selected.

"(C) An analysis of the following:

"(i) The projected or actual carbon footprint over the full life cycle of the various sustainable building materials evaluated in the pilot program.

"(ii) The life cycle costs of the various sustainable building materials evaluated in the pilot program.

"(iii) The resilience to extreme weather events of the various sustainable building materials evaluated in the pilot program.

"(iv) Any impact on construction timeliness of using the various sustainable building materials evaluated in the pilot program.

"(v) The cost effectiveness of the military construction projects conducted under the pilot program using sustainable building materials as compared to other materials historically used in military construction.

"(D) Any updated guidance the Under Secretary of Defense for Acquisition and Sustainment has released in relation to the procurement policy for future military construction projects based on comparable benefits realized from use of sustainable building materials, including guidance on prioritizing sustainable materials in establishing evaluation criteria for military construction project contracts when technically feasible.

"(g) Sustainable Building Materials Defined.—In this section, the term 'sustainable building material' means any building material the use of which will reduce carbon emissions over the life cycle of the building. The term includes mass timber, concrete, and other carbon-reducing materials."

Pilot Program To Authorize Additional Military Construction Projects for Child Development Centers at Military Installations

Pub. L. 116–283, div. B, title XXVIII, §2865, Jan. 1, 2021, 134 Stat. 4360, provided that:

"(a) Authorization of Additional Projects.—Each Secretary of a military department shall conduct a pilot program under which the Secretary may carry out military construction projects for child development centers at military installations, as specified in the funding table in section 4601 of a National Defense Authorization Act for a fiscal year covered by the pilot program. The military construction projects authorized under the pilot program are in addition to other military construction projects authorized by this Act or other National Defense Authorization Acts for fiscal years covered by the pilot program.

"(b) Reporting Requirement as Condition of Authorization.—

"(1) Report required.—Not later than 90 days after the date of the enactment of a National Defense Authorization Act for a fiscal year covered by the pilot program, the Secretary of the military department concerned shall submit to the congressional defense committees [Committees on Armed Services and Appropriations of the Senate and the House of Representatives] a report that describes the location, title, and cost, together with a Department of Defense Form 1391, for each military construction project the Secretary proposes to carry out under the pilot program pursuant to that National Defense Authorization Act.

"(2) Timing of availability of funds.—No funds may be obligated or expended for a military construction project under the pilot program—

"(A) unless the project is included in a report submitted under paragraph (1); and

"(B) until the expiration of the 30-day period beginning on the date on which the Secretary concerned submits the report under paragraph (1) in which the project is included.

"(c) Expiration of Authorization.—Section 2002 of a National Defense Authorization Act for a fiscal year covered by the pilot program shall apply with respect to the authorization of a military construction project carried out under the pilot program pursuant to that National Defense Authorization Act in the same manner as such section applies to the authorization of military construction projects contained in titles XXI through XXIII of that National Defense Authorization Act.

"(d) Covered Fiscal Years.—The pilot program shall be carried out for each of fiscal years 2021 through 2025, as provided in the National Defense Authorization Act for that fiscal year."

Amendment of Unified Facilities Criteria To Promote Military Installation Resilience, Energy Resilience, Energy and Climate Resiliency, and Cyber Resilience

Pub. L. 116–92, div. B, title XXVIII, §2804, Dec. 20, 2019, 133 Stat. 1882, provided that:

"(a) Amendment Required.—

"(1) In general.—Not later than September 1, 2020, the Secretary of Defense shall amend the Unified Facility Criteria relating to military construction planning and design, to ensure that building practices and standards of the Department of Defense promote military installation resilience, energy resilience, energy and climate resiliency, and cyber resilience.

"(2) Considerations and consultation.—In preparing amendments pursuant to paragraph (1), the Secretary of Defense—

"(A) shall take into account historical data, current conditions, and sea level rise projections; and

"(B) may consult with the heads of other Federal departments and agencies with expertise regarding military installation resilience, energy resilience, energy and climate resiliency, and cyber resilience.

"(b) Conditional Availability of Funds.—Not more than 25 percent of the funds authorized to be appropriated for fiscal year 2020 for Department of Defense planning and design accounts relating to military construction projects may be obligated until the date on which the Secretary of Defense submits to the Committees on Armed Services of the House of Representatives and the Senate a certification that the Secretary—

"(1) has initiated the amendment process required by subsection (a)(1); and

"(2) intends to complete such process by September 1, 2020.

"(c) Update of Unified Facilities Criteria to Include Changing Environmental Condition Projections.—[Amended section 2805(c) of Pub. L. 115–232, set out as a note under section 2864 of this title.]

"(d) Implementation of Unified Facilities Criteria Amendments.—

"(1) Implementation.—Any Department of Defense Form 1391 submitted to Congress after September 1, 2020 shall comply with the Unified Facility Criteria, as amended pursuant to this section.

"(2) Certification.—Not later than March 1, 2021, the Secretary of Defense shall certify to the Committees on Armed Services of the House of Representatives and the Senate the completion and full incorporation into military construction planning and design—

"(A) amendments made pursuant to subsection (a); and

"(B) amendments made pursuant to section 2805(c) of the Military Construction Authorization Act for Fiscal Year 2019 (division B of Public Law 115–232; 132 Stat. 2262; 10 U.S.C. 2864 note), as amended by subsection (c).

"(e) Annual Review.—Beginning with fiscal year 2022, and annually thereafter, the Secretary of Defense shall conduct a review comparing the Unified Facility Criteria and industry best practices, for the purpose of ensuring that military construction building practices and standards of the Department of Defense relating to military installation resilience, energy resilience, energy and climate resiliency, and cyber resilience remain up-to-date.

"(f) Definitions.—In this section:

"(1) The terms 'energy resilience' and 'military installation resilience' have the meanings given those terms in section 101(e) of title 10, United States Code [now 10 U.S.C. 101(f)].

"(2) The term 'energy and climate resiliency' has the meaning given that term in section 2864 of title 10, United States Code."

Modification to Department of Defense Form 1391 Regarding Consideration of Potential Long-Term Adverse Environmental Effects

Pub. L. 116–92, div. B, title XXVIII, §2805, Dec. 20, 2019, 133 Stat. 1884, provided that:

"(a) Modification.—

"(1) Certification requirement.—The Secretary of Defense shall modify Department of Defense Form 1391 to require, with respect to any proposed major or minor military construction project requiring congressional notification or approval, the inclusion of a certification by the Secretary of Defense or the Secretary of the military department concerned that the proposed military construction project takes into consideration—

"(A) the potential adverse consequences of long-term changes in environmental conditions, such as increasingly frequent extreme weather events, that could affect the military installation resilience of the installation for which the military construction project is proposed; and

"(B) building requirements in effect for the locality in which the military construction project is proposed and industry best practices that are developed to withstand extreme weather events and other consequences of changes in environmental conditions.

"(2) Elements of certification.—As part of the certification required by paragraph (1) for a proposed military construction project, the Secretary concerned shall identify the potential changes in environmental conditions, such as increasingly frequent extreme weather events, considered and addressed under subparagraphs (A) and (B) of paragraph (1).

"(b) Relation to Recent Modification Requirement.—The modification of Department of Defense Form 1391 required by subsection (a) is in addition to, and expands upon, the modification of Department of Defense Form 1391 with respect to flood risk disclosure for military construction required by section 2805(a) of the Military Construction Authorization Act for Fiscal Year 2019 (division B of Public Law 115–232; 132 Stat. 2262; 10 U.S.C. 2802 note).

"(c) Military Installation Resilience Defined.—In this section, the term 'military installation resilience' has the meaning given that term in section 101(e)(8) of title 10, United States Code [now 10 U.S.C. 101(f)(8)]."

Pilot Program To Extend Service Life of Roads and Runways Under the Jurisdiction of the Secretary of Defense

Pub. L. 116–92, div. B, title XXVIII, §2865, Dec. 20, 2019, 133 Stat. 1901, provided that:

"(a) Pilot Program Authorized.—The Secretary of Defense, in consultation with the Secretary of Transportation, may carry out a pilot program to design, build, and test technologies, techniques, and materials in order to extend the service life of roads and runways under the jurisdiction of the Secretary of Defense.

"(b) Scope.—The pilot program under subsection (a) shall include the following:

"(1) The design, testing, and assembly of technologies and systems suitable for pavement applications.

"(2) Research, development, and testing of pavement materials for use in different geographic areas in the United States.

"(3) The design and procurement of platforms and equipment to test the performance, cost, feasibility, and effectiveness of the technologies, systems, and materials described in paragraphs (1) and (2).

"(c) Award of Contracts or Grants.—

"(1) In general.—The Secretary of Defense may carry out the pilot program under subsection (a) through the award of contracts or grants for the designing, building, or testing of technologies, techniques, and materials under the pilot program.

"(2) Merit-based selection.—Any award of a contract or grant under the pilot program under subsection (a) shall be made using merit-based selection procedures.

"(d) Report.—

"(1) In general.—Not later than two years after the commencement of the pilot program under subsection (a), the Secretary of Defense shall submit to the congressional defense committees [Committees on Armed Services and Appropriations of the Senate and the House of Representatives] a report on the pilot program.

"(2) Contents.—The report under paragraph (1) with respect to the pilot program shall include the following:

"(A) An assessment of the effectiveness of activities under the pilot program in improving the service life of roads and runways under the jurisdiction of the Secretary.

"(B) An analysis of the potential lifetime cost savings and reduction in energy demands associated with the extended service life of such roads and runways.

"(e) Termination of Authority.—The pilot program under subsection (a) shall terminate on September 30, 2024."

Updates and Modifications to Department of Defense Form 1391, Unified Facilities Criteria, and Military Installation Master Plans

Pub. L. 117–81, div. B, title XXVIII, §2805(d), Dec. 27, 2021, 135 Stat. 2189, provided that:

"(1) Amendment required.—Not later than September 1, 2022, the Secretary of Defense shall amend the Unified Facilities Criteria relating to military construction planning and design to ensure that building practices and standards of the Department of Defense incorporate the minimum flood mitigation requirements of section 2805(a) of the Military Construction Authorization Act for Fiscal Year 2019 (division B of Public Law 115–232; 132 Stat. 2262; 10 U.S.C. 2802 note), as amended by this section.

"(2) Implementation of unified facilities criteria amendments.—

"(A) Implementation.—Any Department of Defense Form 1391 submitted to Congress after September 1, 2022, shall comply with the Unified Facilities Criteria, as amended pursuant to paragraph (1).

"(B) Certification.—Not later than March 1, 2023, the Secretary of Defense shall certify to the Committees on Armed Services of the House of Representatives and the Senate the completion of the amendment process required by paragraph (1) and the full incorporation of the amendments into military construction planning and design."

Pub. L. 115–232, div. B, title XXVIII, §2805(a), (b), Aug. 13, 2018, 132 Stat. 2262, as amended by Pub. L. 116–92, div. B, title XXVIII, §2806, Dec. 20, 2019, 133 Stat. 1884; Pub. L. 117–81, div. B, title XXVIII, §2805(a)–(c), Dec. 27, 2021, 135 Stat. 2189, provided that:

"(a) Flood Risk Disclosure for Military Construction.—

"(1) In general.—The Secretary of Defense shall modify Department of Defense Form 1391 to require, with respect to any proposed major or minor military construction project requiring congressional notification or approval—

"(A) disclosure whether a proposed project will be sited within or partially within a 100-year floodplain or a 500-year floodplain if outside a 100-year floodplain, according to the most recent available Federal Emergency Management Agency flood hazard data, or will be impacted by projected current and future mean sea level fluctuations over the lifetime of the project; and

"(B) if the proposed project will be sited within or partially within a floodplain described in subparagraph (A) or will be impacted by projected current and future mean sea level fluctuations over the lifetime of the project, the specific risk mitigation plan.

"(2) Delineation of floodplain.—To the extent that Federal Emergency Management Agency flood hazard data are not available for a proposed major or minor military construction site, the Secretary concerned shall establish a process for delineating the 100-year floodplain using risk analysis that is consistent with the standards used to inform Federal flood risk assessments.

"(3) Reporting requirements.—For proposed projects that are to be sited within or partially within a 100-year floodplain or are to be impacted by projected current and future mean sea level fluctuations over the lifetime of the project, the Secretary concerned shall submit to the congressional defense committees [Committees on Armed Services and Appropriations of the Senate and the House of Representatives] a report with the following:

"(A) An assessment of flood vulnerability for the proposed project using hydrologic, hydraulic, and hydrodynamic data, methods, and analysis that integrate current and projected changes in flooding based on climate science over the anticipated service life of the facility and future forecasted land use changes.

"(B) Any information concerning alternative construction sites that were considered, and an explanation of why those sites do not satisfy mission requirements.

"(C) A description of planned flood mitigation measures.

"(D) A description of how the proposed project has taken into account projected current and future flood risk and mean sea level fluctuations over the lifetime of the project.

"(4) Minimum flood mitigation requirements.—When mitigating the flood risk of a major or minor military construction project within or partially within the 100-year floodplain or that will be impacted by projected current and future mean sea level fluctuations over the lifetime of the project, the Secretary concerned shall require any mitigation plan to assume—

"(A) an additional 2 feet above the base flood elevation for non-mission critical facilities, as determined by the Secretary;

"(B) an additional 3 feet above the base flood elevation for mission-critical facilities, as determined by the Secretary; and

"(C) any additional flooding that will result from projected current and future flood risk and mean sea level fluctuations over the lifetime of the project.

"(b) Disclosure Requirements for Department of Defense Form 1391.—Not later than 30 days after the date of the enactment of this Act [Aug. 13, 2018], the Secretary of Defense shall amend Department of Defense Form 1391 to require, for each requested military construction project—

"(1) disclosure whether the project was included in the prior year's future-years defense program submitted to Congress pursuant to section 221 of title 10, United States Code; and

"(2) inclusion of an energy study or life cycle analysis."

Requirements Related to Providing World Class Military Medical Centers

Pub. L. 111–383, div. B, title XXVIII, §2852, Jan. 7, 2011, 124 Stat. 4475, provided that:

"(a) Unified Construction Standard for Military Construction and Repairs to Military Medical Centers.—Not later than 180 days after the date of the enactment of this Act [Jan. 7, 2011], the Secretary of Defense shall establish a unified construction standard for military construction and repairs for military medical centers that provides a single standard of care. This standard shall also include—

"(1) size standards for operating rooms and patient recovery rooms; and

"(2) such other construction standards that the Secretary considers necessary to support military medical centers.

"(b) Independent Review Panel.—

"(1) Establishment; purpose.—The Secretary of Defense shall establish an independent advisory panel for the purpose of—

"(A) reviewing the unified construction standards established pursuant to subsection (a) to determine the standards consistency with industry practices and benchmarks for world class medical construction;

"(B) reviewing ongoing construction programs within the Department of Defense to ensure medical construction standards are uniformly applied across applicable military medical centers;

"(C) assessing the approach of the Department of Defense approach to planning and programming facility improvements with specific emphasis on—

"(i) facility selection criteria and proportional assessment system; and

"(ii) facility programming responsibilities between the Assistant Secretary of Defense for Health Affairs and the Secretaries of the military departments;

"(D) assessing whether the Comprehensive Master Plan for the National Capital Region Medical, dated April 2010, is adequate to fulfill statutory requirements, as required by section 2714 of the Military Construction Authorization Act for Fiscal Year 2010 (division B of Public Law 111–84; 123 Stat. 2656), to ensure that the facilities and organizational structure described in the plan result in world class military medical centers in the National Capital Region; and

"(E) making recommendations regarding any adjustments of the master plan referred to in subparagraph (D) that are needed to ensure the provision of world class military medical centers and delivery system in the National Capital Region.

"(2) Members.—

"(A) Appointments by secretary.—The panel shall be composed of such members as determined by the Secretary of Defense, except that the Secretary shall include as members—

"(i) medical facility design experts;

"(ii) military healthcare professionals;

"(iii) representatives of premier health care centers in the United States; and

"(iv) former retired senior military officers with joint operational and budgetary experience.

"(B) Congressional appointments.—The chairmen and ranking members of the Committees on the Armed Services of the Senate and House of Representatives may each designate one member of the panel.

"(C) Term.—Members of the panel may serve on the panel until the termination date specified in paragraph (7).

"(D) Compensation.—While performing duties on behalf of the panel, a member and any adviser referred to in paragraph (4) shall be reimbursed under Government travel regulations for necessary travel expenses.

"(3) Meetings.—The panel shall meet not less than quarterly. The panel or its members may make other visits to military treatment centers and military headquarters in connection with the duties of the panel.

"(4) Staff and advisors.—The Secretary of Defense shall provide necessary administrative staff support to the panel. The panel may call in advisers for consultation.

"(5) Reports.—

"(A) Initial report.—Not later than 120 days after the first meeting of the panel, the panel shall submit to the Secretary of Defense a written report containing—

"(i) an assessment of the adequacy of the plan of the Department of Defense to address the items specified in subparagraphs (A) through (E) of paragraph (1) relating to the purposes of the panel; and

"(ii) the recommendations of the panel to improve the plan.

"(B) Additional reports.—Not later than February 1, 2011, and each February 1 thereafter until termination of the panel, the panel shall submit to the Secretary of Defense a report on the findings and recommendations of the panel to address any deficiencies identified by the panel.

"(6) Assessment of recommendations.—Not later than 30 days after the date of the submission of each report under paragraph (5), the Secretary of Defense shall submit to the congressional defense committees [Committees on Armed Services and Appropriations of the Senate and the House of Representatives] a report including—

"(A) a copy of the panel's assessment;

"(B) an assessment by the Secretary of the findings and recommendations of the panel; and

"(C) the plans of the Secretary for addressing such findings and recommendations.

"(7) Termination.—The panel shall terminate on September 30, 2015.

"(c) Definitions.—In this section:

"(1) National capital region.—The term 'National Capital Region' has the meaning given the term in section 2674(f) of title 10, United States Code.

"(2) World class military medical center.—The term 'world class military medical center' has the meaning given the term 'world class military medical facility' by the National Capital Region Base Realignment and Closure Health Systems Advisory Subcommittee of the Defense Health Board in appendix B of the report titled 'Achieving World Class—An Independent Review of the Design Plans for the Walter Reed National Military Medical Center and the Fort Belvoir Community Hospital' and published in May 2009, as required by section 2721 of the Military Construction Authorization Act for Fiscal Year 2009 (division B of Public Law 110–417; 122 Stat. 4716)."

Damage to Aviation Facilities Caused by Alkali Silica Reactivity

Pub. L. 106–398, §1 [[div. A], title III, §389], Oct. 30, 2000, 114 Stat. 1654, 1654A-89, provided that:

"(a) Assessment of Damage and Prevention and Mitigation Technology.—The Secretary of Defense shall require the Secretaries of the military departments to assess—

"(1) the damage caused to aviation facilities of the Armed Forces by alkali silica reactivity; and

"(2) the availability of technologies capable of preventing, treating, or mitigating alkali silica reactivity in hardened concrete structures and pavements.

"(b) Evaluation of Technologies.—(1) Taking into consideration the assessment under subsection (a), the Secretary of each military department may conduct a demonstration project at a location selected by the Secretary concerned to test and evaluate the effectiveness of technologies intended to prevent, treat, or mitigate alkali silica reactivity in hardened concrete structures and pavements.

"(2) The Secretary of Defense shall ensure that the locations selected for the demonstration projects represent the diverse operating environments of the Armed Forces.

"(c) New Construction.—The Secretary of Defense shall develop specific guidelines for appropriate testing and use of lithium salts to prevent alkali silica reactivity in new construction of the Department of Defense.

"(d) Completion of Assessment and Demonstration.—The assessment conducted under subsection (a) and the demonstration projects, if any, conducted under subsection (b) shall be completed not later than September 30, 2006.

"(e) Delegation of Authority.—The authority to conduct the assessment under subsection (a) may be delegated only to the Chief of Engineers of the Army, the Commander of the Naval Facilities Engineering Command, and the Civil Engineer of the Air Force.

"(f) Limitation on Expenditures.—The Secretary of Defense and the Secretaries of the military departments may not expend more than a total of $5,000,000 to conduct both the assessment under subsection (a) and all of the demonstration projects under subsection (b)."

Reports Relating to Military Construction for Facilities Supporting New Weapon Systems

Pub. L. 102–190, div. B, title XXVIII, §2868, Dec. 5, 1991, 105 Stat. 1562, as amended by Pub. L. 108–136, div. A, title X, §1031(c)(2), Nov. 24, 2003, 117 Stat. 1604, which required the Secretary of Defense to submit to Congress a report relating to the permanent basing of a new weapon system not later than 30 days after selecting a site or sites for such permanent basing, was repealed by Pub. L. 112–81, div. A, title X, §1062(m), Dec. 31, 2011, 125 Stat. 1586.

§2803. Emergency construction

(a) Subject to subsections (b) and (c), the Secretary concerned may carry out a military construction project not otherwise authorized by law if the Secretary determines (1) that the project is vital to the national security or to the protection of health, safety, or the quality of the environment, and (2) that the requirement for the project is so urgent that deferral of the project for inclusion in the next Military Construction Authorization Act would be inconsistent with national security or the protection of health, safety, or environmental quality, as the case may be.

(b) When a decision is made to carry out a military construction project under this section, the Secretary concerned shall submit a report to the appropriate committees of Congress on that decision. Each such report shall include (1) the justification for the project and the current estimate of the cost of the project, (2) the justification for carrying out the project under this section, and (3) a statement of the source of the funds to be used to carry out the project. The project may then be carried out only after the end of the five-day period beginning on the date the notification is received by such committees in an electronic medium pursuant to section 480 of this title.

(c)(1) The maximum amount that the Secretary concerned may obligate in any fiscal year under this section is $50,000,000.

(2) A project carried out under this section shall be carried out within the total amount of funds appropriated for military construction that have not been obligated.

(Added Pub. L. 97–214, §2(a), July 12, 1982, 96 Stat. 154; amended Pub. L. 102–190, div. B, title XXVIII, §§2803, 2870(2), Dec. 5, 1991, 105 Stat. 1537, 1562; Pub. L. 102–484, div. A, title X, §1053(9), Oct. 23, 1992, 106 Stat. 2502; Pub. L. 108–136, div. A, title X, §1031(a)(34), div. B, title XXVIII, §2802, Nov. 24, 2003, 117 Stat. 1600, 1719; Pub. L. 109–364, div. B, title XXVIII, §2801, Oct. 17, 2006, 120 Stat. 2466; Pub. L. 112–81, div. A, title X, §1064(9), Dec. 31, 2011, 125 Stat. 1587; Pub. L. 115–91, div. B, title XXVIII, §2801(a)(1), Dec. 12, 2017, 131 Stat. 1840.)


Editorial Notes

Amendments

2017—Subsec. (b). Pub. L. 115–91 struck out "in writing" after "submit a report" and "or, if earlier, the end of the seven-day period beginning on the date on which a copy of the notification is provided" after "such committees" and substituted "five-day period" for "seven-day period".

2011—Subsec. (b). Pub. L. 112–81 substituted "after the end of the seven-day period" for "after the end of the 21-day period".

2006—Subsec. (c)(1). Pub. L. 109–364 substituted "$50,000,000" for "$45,000,000".

2003—Subsec. (b). Pub. L. 108–136, §1031(a)(34), inserted before period at end "or, if earlier, the end of the seven-day period beginning on the date on which a copy of the notification is provided in an electronic medium pursuant to section 480 of this title".

Subsec. (c)(1). Pub. L. 108–136, §2802, substituted "$45,000,000" for "$30,000,000".

1992—Subsec. (b). Pub. L. 102–484 made technical amendment to directory language of Pub. L. 102–190, §2870(2). See 1991 Amendment note below.

1991—Subsec. (a). Pub. L. 102–190, §2803, substituted "or to the protection of health, safety, or the quality of the environment, and" for ", and" in cl. (1) and inserted "or the protection of health, safety, or environmental quality, as the case may be" before period at end of cl. (2).

Subsec. (b). Pub. L. 102–190, §2870(2), as amended by Pub. L. 102–484, struck out ", or after each such committee has approved the project, if the committee approves the project before the end of that period" after "by such committees".


Statutory Notes and Related Subsidiaries

Effective Date of 1992 Amendment

Pub. L. 102–484, div. A, title X, §1053, Oct. 23, 1992, 106 Stat. 2501, provided that the amendment made by that section is effective Dec. 5, 1991.

Effective Date

For effective date and applicability of section, see section 12(a) of Pub. L. 97–214, set out as a note under section 2801 of this title.

§2804. Contingency construction

(a) Within the amount appropriated for such purpose, the Secretary of Defense may carry out a military construction project not otherwise authorized by law, or may authorize the Secretary of a military department to carry out such a project, if the Secretary of Defense determines that deferral of the project for inclusion in the next Military Construction Authorization Act would be inconsistent with national security or national interest.

(b) When a decision is made to carry out a military construction project under this section, the Secretary of Defense shall submit a report to the appropriate committees of Congress on that decision. Each such report shall include the justification for the project, the current estimate of the cost of the project, and the justification for carrying out the project under this section. The project may then be carried out only after the end of the seven-day period beginning on the date the notification is received by such committees in an electronic medium pursuant to section 480 of this title.

(Added Pub. L. 97–214, §2(a), July 12, 1982, 96 Stat. 155; amended Pub. L. 102–190, div. B, title XXVIII, §2870(3), Dec. 5, 1991, 105 Stat. 1563; Pub. L. 108–136, div. A, title X, §1031(a)(35), Nov. 24, 2003, 117 Stat. 1600; Pub. L. 109–163, div. B, title XXVIII, §2801(a), Jan. 6, 2006, 119 Stat. 3504; Pub. L. 115–91, div. B, title XXVIII, §2801(a)(2), Dec. 12, 2017, 131 Stat. 1840; Pub. L. 116–92, div. A, title XVII, §1731(a)(54), Dec. 20, 2019, 133 Stat. 1815; Pub. L. 116–283, div. A, title X, §1081(a)(44), Jan. 1, 2021, 134 Stat. 3873.)


Editorial Notes

Amendments

2021—Subsec. (b). Pub. L. 116–283 struck out "; and" after "seven-day period".

2019—Subsec. (b). Pub. L. 116–92 substituted "include the justification" for "include (1) the justification", "project, the current" for "project and the current", and "and the justification" for "and (2) the justification".

2017—Subsec. (b). Pub. L. 115–91 struck out "in writing" after "submit a report" and "or, if earlier, the end of the seven-day period beginning on the date on which a copy of the notification is provided" after "such committees" and substituted "seven-day period; and" for "14-day period".

2006—Subsec. (b). Pub. L. 109–163 substituted "14-day period" for "21-day period" and "seven-day period" for "14-day period".

2003—Subsec. (b). Pub. L. 108–136 inserted before period at end "or, if earlier, the end of the 14-day period beginning on the date on which a copy of the notification is provided in an electronic medium pursuant to section 480 of this title".

1991—Subsec. (b). Pub. L. 102–190 struck out before period at end ", or after each such committee has approved the project, if the committees approve the project before the end of that period".


Statutory Notes and Related Subsidiaries

Effective Date

For effective date and applicability of section, see section 12(a) of Pub. L. 97–214, set out as a note under section 2801 of this title.

Authority to Use Operation and Maintenance Funds for Certain Construction Projects Outside the United States

Pub. L. 108–136, div. B, title XXVIII, §2808, Nov. 24, 2003, 117 Stat. 1723, as amended by Pub. L. 108–375, div. B, title XXVIII, §2810, Oct. 28, 2004, 118 Stat. 2128; Pub. L. 109–163, div. B, title XXVIII, §2809, Jan. 6, 2006, 119 Stat. 3508; Pub. L. 109–364, div. B, title XXVIII, §2802, Oct. 17, 2006, 120 Stat. 2466; Pub. L. 110–181, div. B, title XXVIII, §2801(a)–(d), Jan. 28, 2008, 122 Stat. 538, 539; Pub. L. 110–417, div. B, title XXVIII, §2806, Oct. 14, 2008, 122 Stat. 4724; Pub. L. 111–84, div. B, title XXVIII, §2806, Oct. 28, 2009, 123 Stat. 2662; Pub. L. 111–383, div. B, title XXVIII, §2804, Jan. 7, 2011, 124 Stat. 4459; Pub. L. 112–81, div. B, title XXVIII, §2804, Dec. 31, 2011, 125 Stat. 1685; Pub. L. 112–239, div. B, title XXVIII, §2804, Jan. 2, 2013, 126 Stat. 2149; Pub. L. 113–66, div. B, title XXVIII, §2808, Dec. 26, 2013, 127 Stat. 1012; Pub. L. 113–291, div. B, title XXVIII, §2806, Dec. 19, 2014, 128 Stat. 3699; Pub. L. 114–92, div. B, title XXVIII, §2802, Nov. 25, 2015, 129 Stat. 1169; Pub. L. 114–328, div. B, title XXVIII, §2804, Dec. 23, 2016, 130 Stat. 2713; Pub. L. 115–91, div. B, title XXVIII, §2804, Dec. 12, 2017, 131 Stat. 1846; Pub. L. 115–232, div. B, title XXVIII, §2807, Aug. 13, 2018, 132 Stat. 2264; Pub. L. 116–283, div. B, title XXVIII, §2806, Jan. 1, 2021, 134 Stat. 4322; Pub. L. 117–81, div. B, title XXVIII, §2806, Dec. 27, 2021, 135 Stat. 2190; Pub. L. 117–263, div. B, title XXVIII, §2809(a), (b)(1), (3)–(c), 136 Stat. 2996, provided that:

"(a) In General.—The Secretary of Defense may obligate appropriated funds available for operation and maintenance to carry out a construction project outside the United States that the Secretary determines meets each of the following conditions:

"(1) The construction is necessary to meet urgent military operational requirements of a temporary nature involving the use of the Armed Forces in support of a declaration of war, the declaration by the President of a national emergency under section 201 of the National Emergencies Act (50 U.S.C. 1621), or a contingency operation.

"(2) The construction is not carried out at a military installation where the United States is reasonably expected to have a long-term presence.

"(3) The United States has no intention of using the construction after the operational requirements have been satisfied.

"(4) The level of construction is the minimum necessary to meet the temporary operational requirements.

"(b) Notification of Obligation of Funds.—Before using appropriated funds available for operation and maintenance to carry out a construction project outside the United States that has an estimated cost in excess of the amounts authorized for unspecified minor military construction projects under section 2805(c) of title 10, United States Code, the Secretary of Defense shall submit to the congressional committees specified in subsection (d) a notice regarding the construction project. The project may be carried out only after the end of the 14-day period beginning on the date the notice is received by the committees, including when a copy of the notification is provided in an electronic medium pursuant to section 480 of title 10, United States Code. The notice shall include the following:

"(1) Certification that the conditions specified in subsection (a) are satisfied with regard to the construction project.

"(2) A description of the purpose for which appropriated funds available for operation and maintenance are being obligated.

"(3) All relevant documentation detailing the construction project.

"(4) An estimate of the total amount obligated for the construction.

"(c) Annual Limitation on Use of Authority.—(1) The total cost of the construction projects carried out under the authority of this section using, in whole or in part, appropriated funds available for operation and maintenance shall not exceed $50,000,000 during each of the following periods:

"(A) The period beginning October 1, 2021, and ending on the earlier of December 31, 2022, or the date of the enactment of an Act authorizing funds for military activities of the Department of Defense for fiscal year 2023 [Dec. 23, 2022].

"(B) The period beginning October 1, 2022, and ending on the earlier of December 31, 2023, or the date of the enactment of an Act authorizing funds for military activities of the Department of Defense for fiscal year 2024.

"(2) Notwithstanding paragraph (1), the Secretary of Defense may authorize the obligation under this section of not more than an additional $10,000,000 of appropriated funds available for operation and maintenance for a fiscal year if the Secretary determines that the additional funds are needed for costs associated with contract closeouts.

"(3) The total amount of operation and maintenance funds used for a single construction project carried out under the authority of this section shall not exceed $15,000,000. The Secretary of Defense may waive this limitation on a project-by-project basis. This waiver authority may not be delegated.

"(d) Congressional Committees.—The congressional committees referred to in this section are the following:

"(1) The Committee on Armed Services and the Subcommittee on Defense and the Subcommittee on Military Construction, Veterans Affairs, and Related Agencies of the Committee on Appropriations of the Senate.

"(2) The Committee on Armed Services and the Subcommittee on Defense and the Subcommittee on Military Construction, Veterans Affairs, and Related Agencies of the Committee on Appropriations of the House of Representatives.

"(e) Effect of Failure to Submit Project Notifications.—If the advance notice of the proposed obligation of the funds for a construction project required by subsection (b) is not submitted to the congressional committees specified in subsection (d) by the required date, appropriated funds available for operation and maintenance may not be obligated or expended after that date under the authority of this section to carry out construction projects outside the United States until the date on which the notice is finally submitted."

[Pub. L. 117–263, div. B, title XXVIII, §2809(d), Dec. 23, 2022, 136 Stat. 2997, provided that: "The Law Revision Counsel is directed to classify section 2808 of the Military Construction Authorization Act for Fiscal Year 2004 (division B of Public Law 108–136; 117 Stat. 1723), as amended by subsection (a), as a note following section 2804 of title 10, United States Code."]

§2805. Unspecified minor construction

(a) Authority to Carry Out Unspecified Minor Military Construction Projects.—(1) Within an amount equal to 125 percent of the amount authorized by law for such purpose, the Secretary concerned may carry out unspecified minor military construction projects not otherwise authorized by law.

(2) An unspecified minor military construction project is a military construction project or a demolition project that has an approved cost equal to or less than $9,000,000.

(3) Notwithstanding the requirements of this section, the Secretary concerned may use amounts authorized pursuant to another law or regulation to carry out a demolition project described in paragraph (2).

(b) Approval and Congressional Notification.—(1) An unspecified minor military construction project costing more than $750,000 may not be carried out under this section unless approved in advance by the Secretary concerned. This paragraph shall apply even though the project is to be carried out using funds made available to enhance the deployment and mobility of military forces and supplies.

(2) When a decision is made to carry out an unspecified minor military construction project to which paragraph (1) is applicable and which costs more than $4,000,000, the Secretary concerned shall notify the appropriate committees of Congress of that decision, of the justification for the project, and of the estimated cost of the project. The project may then be carried out only after the end of the 14-day period beginning on the date the notification is received by the committees in an electronic medium pursuant to section 480 of this title.

(c) Use of Operation and Maintenance Funds.—The Secretary concerned may spend from appropriations available for operation and maintenance amounts necessary to carry out an unspecified minor military construction project costing not more than $4,000,000.

(d) Laboratory Revitalization.—(1) For the revitalization and recapitalization of laboratories owned by the United States and under the jurisdiction of the Secretary concerned, the Secretary concerned may obligate and expend—

(A) from appropriations available to the Secretary concerned for operation and maintenance, amounts necessary to carry out an unspecified minor military construction project costing not more than $9,000,000, notwithstanding subsection (c); or

(B) from appropriations available to the Secretary concerned for military construction not otherwise authorized by law or from funds authorized to be made available under section 4123(a) of this title, amounts necessary to carry out an unspecified minor military construction project costing not more than $9,000,000.


(2) For purposes of this subsection, an unspecified minor military construction project is a military construction project that (notwithstanding subsection (a)) has an approved cost equal to or less than $9,000,000.

(3) If the Secretary concerned makes a decision to carry out an unspecified minor military construction project to which this subsection applies, the Secretary concerned shall notify the appropriate committees of Congress of that decision, of the justification for the project, and of the estimated cost of the project. The project may then be carried out only after the end of the 14-day period beginning on the date the notification is received by the committees in an electronic medium pursuant to section 480 of this title.

(4) In this subsection, the term "laboratory" includes—

(A) a research, engineering, and development center; and

(B) a test and evaluation activity.


(e) Prohibition on Use for New Housing Units.—Military family housing projects for construction of new housing units may not be carried out under the authority of this section.

(f) Adjustment of Dollar Limitations for Location.—

(1) Adjustment of limitations.—Each fiscal year, the Secretary concerned shall adjust the dollar limitations specified in this section applicable to an unspecified minor military construction project to reflect the area construction cost index for military construction projects published by the Department of Defense during the prior fiscal year for the location of the project, except that no limitation specified in this section may exceed $14,000,000 as the result of any adjustment made under this paragraph.

[(2) Repealed. Pub. L. 118–31, div. B, title XXVIII, §2803(2), Dec. 22, 2023, 137 Stat. 744.]

[(3) Repealed. Pub. L. 118–31, div. B, title XXVIII, §2802(c)(2), Dec. 22, 2023, 137 Stat. 743.]


(g) Defense Laboratory Modernization Program.—(1) Using amounts appropriated or otherwise made available to the Department of Defense for research, development, test, and evaluation, the Secretary of Defense may fund a military construction project described in paragraph (4) at any of the following:

(A) A Department of Defense science and technology reinvention laboratory (as designated under section 4121(b) of this title).

(B) A Department of Defense federally funded research and development center that functions primarily as a research laboratory.

(C) A Department of Defense facility in support of a technology development program that is consistent with the fielding of offset technologies as described in section 218 of the National Defense Authorization Act for Fiscal Year 2016 (Public Law 114–92; 10 U.S.C. note 4811).

(D) A Department of Defense research, development, test, and evaluation facility that is not designated as a science and technology reinvention laboratory, but nonetheless is involved with developmental test and evaluation.


(2) Subject to the condition that a military construction project under paragraph (1) be authorized in a Military Construction Authorization Act, the authority to carry out the military construction project includes authority for—

(A) surveys, site preparation, and advanced planning and design;

(B) acquisition, conversion, rehabilitation, and installation of facilities;

(C) acquisition and installation of equipment and appurtenances integral to the project; acquisition and installation of supporting facilities (including utilities) and appurtenances incident to the project; and

(D) planning, supervision, administration, and overhead expenses incident to the project.


(3)(A) The Secretary of Defense shall include military construction projects proposed to be carried out under paragraph (1) in the budget justification documents for the Department of Defense submitted to Congress in connection with the budget for a fiscal year submitted under 1105 of title 31.

(B) Not less than 14 days prior to the first obligation of funds described in paragraph (1) for a military construction project to be carried out under such paragraph, the Secretary of Defense shall submit to the congressional defense committees a notification providing an updated construction description, cost, and schedule for the project and any other matters regarding the project as the Secretary considers appropriate.

(4) The authority provided by paragraph (1) to fund military construction projects using amounts appropriated or otherwise made available for research, development, test, and evaluation is limited to military construction projects that the Secretary of Defense, in the budget justification documents exhibits submitted pursuant to paragraph (3)(A), determines—

(A) will support research and development activities at laboratories described in paragraph (1);

(B) will establish facilities that will have significant potential for use by entities outside the Department of Defense, including universities, industrial partners, and other Federal agencies;

(C) are endorsed for funding by more than one military department or Defense Agency; and

(D) cannot be fully funded within the thresholds otherwise specified in this section.


(5) The maximum amount of funds appropriated or otherwise made available for research, development, test, and evaluation that may be obligated in any fiscal year for military construction projects under paragraph (1) is $150,000,000.

(6)(A) In addition to the authority provided to the Secretary of Defense under paragraph (1) to use amounts appropriated or otherwise made available for research, development, test, and evaluation for a military construction project referred to in such subsection, the Secretary of the military department concerned may use amounts appropriated or otherwise made available for research, development, test, and evaluation to obtain architectural and engineering services and to carry out construction design in connection with such a project.

(B) In the case of architectural and engineering services and construction design to be undertaken under this paragraph for which the estimated cost exceeds $1,000,000, the Secretary concerned shall notify the appropriate committees of Congress of the scope of the proposed project and the estimated cost of such services before the initial obligation of funds for such services. The Secretary may then obligate funds for such services only after the end of the 14-day period beginning on the date on which the notification is received by the committees in an electronic medium pursuant to section 480 of this title.

(Added Pub. L. 97–214, §2(a), July 12, 1982, 96 Stat. 155; amended Pub. L. 99–167, title VIII, §809, Dec. 3, 1985, 99 Stat. 989; Pub. L. 99–661, div. B, title VII, §2702(a), Nov. 14, 1986, 100 Stat. 4040; Pub. L. 100–180, div. B, subdiv. 3, title I, §2310, Dec. 4, 1987, 101 Stat. 1217; Pub. L. 101–510, div. A, title XIII, §1301(16), Nov. 5, 1990, 104 Stat. 1668; Pub. L. 102–190, div. B, title XXVIII, §§2807, 2870(4), Dec. 5, 1991, 105 Stat. 1540, 1563; Pub. L. 104–106, div. B, title XXVIII, §§2811(a), 2812, Feb. 10, 1996, 110 Stat. 552; Pub. L. 104–201, div. B, title XXVIII, §2801(a), Sept. 23, 1996, 110 Stat. 2787; Pub. L. 105–85, div. B, title XXVIII, §2801, Nov. 18, 1997, 111 Stat. 1989; Pub. L. 107–107, div. B, title XXVIII, §2801, Dec. 28, 2001, 115 Stat. 1305; Pub. L. 108–136, div. A, title X, §1031(a)(36), Nov. 24, 2003, 117 Stat. 1600; Pub. L. 110–181, div. B, title XXVIII, §§2803, 2804, Jan. 28, 2008, 122 Stat. 539; Pub. L. 111–84, div. B, title XXVIII, §2801(a)(1), (2), (b), Oct. 28, 2009, 123 Stat. 2660; Pub. L. 112–81, div. B, title XXVIII, §2802(a), (b), Dec. 31, 2011, 125 Stat. 1684; Pub. L. 113–66, div. B, title XXVIII, §2801(a), Dec. 26, 2013, 127 Stat. 1006; Pub. L. 113–291, div. B, title XXVIII, §2802, Dec. 19, 2014, 128 Stat. 3695; Pub. L. 114–328, div. B, title XXVIII, §2801, Dec. 23, 2016, 130 Stat. 2712; Pub. L. 115–91, div. A, title II, §220(c)(2), div. B, title XXVIII, §§2801(a)(3), 2802, 2803, Dec. 12, 2017, 131 Stat. 1333, 1840, 1845, 1846; Pub. L. 116–92, div. A, title XVII, §1731(a)(55), Dec. 20, 2019, 133 Stat. 1815; Pub. L. 116–283, div. A, title XVIII, §1843(c), div. B, title XXVIII, §2802, Jan. 1, 2021, 134 Stat. 4245, 4319; Pub. L. 117–81, div. A, title XVII, §1701(u)(4)(B), Dec. 27, 2021, 135 Stat. 2153; Pub. L. 117–263, div. B, title XXVIII, §§2802, 2803(a), 2804, Dec. 23, 2022, 136 Stat. 2992, 2994; Pub. L. 118–31, div. B, title XXVIII, §§2802(a)–(c), 2803, Dec. 22, 2023, 137 Stat. 743, 744.)


Editorial Notes

Codification

Another section 2803(a) of Pub. L. 117–263 (136 Stat. 2970), is set out as a note under section 2687 of this title.

Amendments

2023—Subsec. (a)(2). Pub. L. 118–31, §2802(a)(1), (b)(1), inserted "or a demolition project" after "is a military construction project" and substituted "$9,000,000" for "$6,000,000".

Subsec. (a)(3). Pub. L. 118–31, §2802(a)(2), added par. (3).

Subsec. (b)(2). Pub. L. 118–31, §2802(b)(2), substituted "$4,000,000" for "$2,000,000".

Subsec. (c). Pub. L. 118–31, §2802(b)(3), substituted "$4,000,000" for "$2,000,000".

Subsec. (d)(1)(A). Pub. L. 118–31, §2802(b)(4)(A)(i), substituted "$9,000,000" for "$6,000,000".

Subsec. (d)(1)(B). Pub. L. 118–31, §2802(b)(4)(A)(ii), substituted "$9,000,000" for "$6,000,000".

Subsec. (d)(2). Pub. L. 118–31, §2802(b)(4)(B), substituted "$9,000,000" for "$6,000,000".

Subsec. (f)(1). Pub. L. 118–31, §§2802(c)(1), 2803(1), struck out "inside the United States" after "construction project" and substituted "$14,000,000" for "$10,000,000".

Subsec. (f)(2). Pub. L. 118–31, §2803(2), struck out par. (2). Text read as follows: "For purposes of paragraph (1), a project shall be considered to be inside the United States if the project is carried out in any of the several States, the District of Columbia, the Commonwealth of Puerto Rico, Guam, American Samoa, the United States Virgin Islands, Wake Island, the Commonwealth of the Northern Mariana Islands, or a former United States Trust Territory now in a Compact of Free Association with the United States."

Subsec. (f)(3). Pub. L. 118–31, §2802(c)(2), struck out par. (3). Text read as follows: "The requirements of this subsection shall not apply with respect to any fiscal year after fiscal year 2027."

2022—Subsec. (d)(5). Pub. L. 117–263, §2804, struck out par. (5) which read as follows: "The authority to carry out a project under this subsection expires on September 30, 2025."

Subsec. (f)(2). Pub. L. 117–263, §2802, substituted "Wake Island, the Commonwealth" for "or the Commonwealth" and inserted ", or a former United States Trust Territory now in a Compact of Free Association with the United States" after "Mariana Islands".

Subsec. (g). Pub. L. 117–263, §2803(a), added subsec. (g).

2021—Subsec. (d)(1)(B). Pub. L. 116–283, §1843(c), as amended by Pub. L. 117–81, §1701(u)(4)(B), substituted "section 4123(a)" for "section 2363(a)".

Subsec. (f)(3). Pub. L. 116–283, §2802, substituted "2027" for "2022".

2019—Subsec. (d)(1)(B). Pub. L. 116–92 inserted "under" after "made available".

2017—Subsec. (a)(2). Pub. L. 115–91, §2802(a), substituted "$6,000,000" for "$3,000,000" and struck out at end "However, if the military construction project is intended solely to correct a deficiency that is life-threatening, health-threatening, or safety-threatening, an unspecified minor military construction project may have an approved cost equal to or less than $4,000,000."

Subsec. (b)(1). Pub. L. 115–91, §2802(b), substituted "$750,000" for "$1,000,000".

Subsec. (b)(2). Pub. L. 115–91, §2802(c), substituted "to which paragraph (1) is applicable and which costs more than $2,000,000" for "to which paragraph (1) is applicable".

Pub. L. 115–91, §2801(a)(3)(A), struck out "in writing" after "shall notify" and "or, if earlier, the end of the 14-day period beginning on the date on which a copy of the notification is provided" after "received by the committees" and substituted "14-day period" for "21-day period".

Subsec. (c). Pub. L. 115–91, §2802(d), substituted "$2,000,000" for "$1,000,000".

Subsec. (d)(1)(B). Pub. L. 115–91, §220(c)(2), substituted "section 2363(a) of this title" for "under section 219(a) of the Duncan Hunter National Defense Authorization Act for Fiscal Year 2009 (Public Law 110–417; 10 U.S.C. 2358 note)".

Subsec. (d)(3). Pub. L. 115–91, §2801(a)(3)(B), struck out "in writing" after "shall notify" and "or, if earlier, the end of the 14-day period beginning on the date on which a copy of the notification is provided" after "received by the committees" and substituted "14-day period" for "21-day period".

Subsec. (f). Pub. L. 115–91, §2803, added subsec. (f).

2016—Subsec. (d)(1). Pub. L. 114–328, §2801(a), substituted "$6,000,000" for "$4,000,000" in subpars. (A) and (B).

Subsec. (d)(2). Pub. L. 114–328, §2801(a), (b)(1), substituted "$6,000,000" for "$4,000,000" in first sentence and struck out second sentence which read as follows: "The Secretary of Defense shall establish procedures for the review and approval of requests from the Secretary of a military department to carry out a construction project under this subsection."

Subsec. (d)(3). Pub. L. 114–328, §2801(b)(2), amended par. (3) generally. Prior to amendment, par. (3) read as follows: "Not later than February 1, 2014, the Secretary of Defense shall submit to the congressional defense committees a report on the use of the authority provided by this subsection. The report shall include a list and description of the construction projects carried out under this subsection, including the location and cost of each project."

Subsec. (d)(5). Pub. L. 114–328, §2801(c), substituted "2025" for "2018".

2014—Subsec. (a)(2). Pub. L. 113–291, §2802(a), substituted "$3,000,000" for "$2,000,000" in first sentence and "$4,000,000" for "$3,000,000" in second sentence.

Subsec. (b)(1). Pub. L. 113–291, §2802(b), substituted "$1,000,000" for "$750,000".

Subsec. (c). Pub. L. 113–291, §2802(c), substituted "$1,000,000" for "$750,000".

2013—Subsec. (d)(1)(A). Pub. L. 113–66, §2801(a)(1), substituted "not more than $4,000,000, notwithstanding subsection (c)" for "not more than $2,000,000".

Subsec. (d)(2). Pub. L. 113–66, §2801(a)(2), substituted "For purposes of this subsection, an unspecified minor military construction project is a military construction project that (notwithstanding subsection (a)) has an approved cost equal to or less than $4,000,000." for "For an unspecified minor military construction project conducted pursuant to this subsection, $2,000,000 shall be deemed to be the amount specified in subsection (b)(1) regarding when advance approval of the project by the Secretary concerned and congressional notification is required."

Subsec. (d)(5). Pub. L. 113–66, §2801(a)(3), substituted "2018" for "2016".

2011—Subsec. (c). Pub. L. 112–81, §2802(a), substituted "The" for "(1) Except as provided in paragraph (2), the" and "not more than $750,000." for "not more than—

"(A) $1,500,000, in the case of an unspecified minor military construction project intended solely to correct a deficiency that is life-threatening, health-threatening, or safety-threatening; or

"(B) $750,000, in the case of any other unspecified minor military construction project.

"(2) The limitations specified in paragraph (1) shall not apply to an unspecified minor military construction project if the project is to be carried out using funds made available to enhance the deployment and mobility of military forces and supplies."

Subsec. (d)(3). Pub. L. 112–81, §2802(b)(1), substituted "February 1, 2014" for "February 1, 2010".

Subsec. (d)(5). Pub. L. 112–81, §2802(b)(2), substituted "September 30, 2016" for "September 30, 2012".

2009—Subsec. (a). Pub. L. 111–84, §2801(a)(1), substituted "Within" for "Except as provided in paragraph (2), within" in par. (1), redesignated the second and third sentences of par. (1) as par. (2), and struck out former par. (2) which read as follows: "A Secretary may not use more than $5,000,000 for exercise-related unspecified minor military construction projects coordinated or directed by the Joint Chiefs of Staff outside the United States during any fiscal year."

Subsec. (c). Pub. L. 111–84, §2801(a)(2), substituted "paragraph (2)" for "paragraphs (2) and (3)" in par. (1), redesignated par. (3) as (2), and struck out former par. (2) which read as follows: "The authority provided in paragraph (1) may not be used with respect to any exercise-related unspecified minor military construction project coordinated or directed by the Joint Chiefs of Staff outside the United States."

Subsec. (d)(1)(B). Pub. L. 111–84, §2801(b)(1), inserted "or from funds authorized to be made available under section 219(a) of the Duncan Hunter National Defense Authorization Act for Fiscal Year 2009 (Public Law 110–417; 10 U.S.C. 2358 note)" after "authorized by law".

Subsec. (d)(3) to (6). Pub. L. 111–84, §2801(b)(2), (3), redesignated pars. (4) to (6) as (3) to (5), respectively, and struck out former par. (3) which read as follows: "For purposes of this subsection, the total amount allowed to be applied in any one fiscal year to projects at any one laboratory shall be limited to the larger of the amounts applicable under paragraph (1)."

2008—Subsec. (a). Pub. L. 110–181, §2804(b)(1), inserted subsec. heading.

Subsec. (a)(1). Pub. L. 110–181, §2803, substituted "$2,000,000" for "$1,500,000".

Subsecs. (b), (c). Pub. L. 110–181, §2804(b)(2), (3), inserted subsec. headings.

Subsecs. (d), (e). Pub. L. 110–181, §2804(a), (b)(4), added subsec. (d), redesignated former subsec. (d) as (e), and inserted subsec. (e) heading.

2003—Subsec. (b)(2). Pub. L. 108–136 inserted before period at end "or, if earlier, the end of the 14-day period beginning on the date on which a copy of the notification is provided in an electronic medium pursuant to section 480 of this title".

2001—Subsec. (b)(1). Pub. L. 107–107, §2801(a), substituted "$750,000" for "$500,000".

Subsec. (c)(1)(A). Pub. L. 107–107, §2801(b)(1), substituted "$1,500,000" for "$1,000,000".

Subsec. (c)(1)(B). Pub. L. 107–107, §2801(b)(2), substituted "$750,000" for "$500,000".

1997—Subsec. (a)(1). Pub. L. 105–85, §2801(c)(1), substituted "unspecified minor military construction projects" for "minor military construction projects", "An unspecified minor" for "A minor", and "an unspecified minor" for "a minor".

Subsec. (b)(1). Pub. L. 105–85, §2801(c)(2), substituted "An unspecified minor" for "A minor".

Pub. L. 105–85, §2801(a), inserted at end "This paragraph shall apply even though the project is to be carried out using funds made available to enhance the deployment and mobility of military forces and supplies."

Subsec. (b)(2). Pub. L. 105–85, §2801(c)(3), substituted "an unspecified minor" for "a minor".

Subsec. (c)(1). Pub. L. 105–85, §2801(c)(4), substituted "unspecified minor military" for "unspecified military" wherever appearing.

Pub. L. 105–85, §2801(b)(1), substituted "paragraphs (2) and (3)" for "paragraph (2)" in introductory provisions.

Subsec. (c)(2). Pub. L. 105–85, §2801(c)(4), substituted "unspecified minor military" for "unspecified military".

Subsec. (c)(3). Pub. L. 105–85, §2801(b)(2), added par. (3).

1996—Subsec. (a)(1). Pub. L. 104–106, §2812, in second sentence, struck out "(1) that is for a single undertaking at a military installation, and (2)" after "is a military construction project".

Pub. L. 104–106, §2811(a)(1), inserted at end "However, if the military construction project is intended solely to correct a deficiency that is life-threatening, health-threatening, or safety-threatening, a minor military construction project may have an approved cost equal to or less than $3,000,000."

Subsec. (c)(1). Pub. L. 104–106, §2811(a)(2), substituted "not more than—" for "not more than $300,000." and added subpars. (A) and (B).

Subsec. (c)(1)(B). Pub. L. 104–201 substituted "$500,000" for "$300,000".

1991—Subsec. (a)(1). Pub. L. 102–190, §2807(a), substituted "$1,500,000" for "$1,000,000".

Subsec. (b)(2). Pub. L. 102–190, §2870(4), in second sentence struck out "(A)" after "carried out only" and ", or (B) after each such committee approves the project, if the committees approve the project before the end of that period" before period at end.

Subsec. (c)(1). Pub. L. 102–190, §2807(b), substituted "$300,000" for "$200,000".

1990—Subsec. (b)(3). Pub. L. 101–510 struck out par. (3) which read as follows: "A project for the relocation of any activity from one installation to another that involves 25 or more full-time civilian employees of the Department of Defense but that is not subject to paragraph (1) may not be carried out under the authority of this section until the appropriate committees of Congress have been notified by the Secretary concerned of the intent to carry out such relocation under the authority of this section."

1987—Subsec. (a). Pub. L. 100–180, §2310(b), designated existing provisions as par. (1), substituted "Except as provided in paragraph (2), within" for "Within", and added par. (2).

Subsec. (c). Pub. L. 100–180, §2310(a), designated existing provisions as par. (1), substituted "Except as provided in paragraph (2), the" for "The", and added par. (2).

1986—Subsec. (a). Pub. L. 99–661, §2702(a)(1), substituted "$1,000,000" for "the amount specified by law as the maximum amount for a minor military construction project".

Subsec. (b)(1). Pub. L. 99–661, §2702(a)(2), substituted "$500,000" for "50 percent of the amount specified by law as the maximum amount for a minor military construction project".

Subsec. (c). Pub. L. 99–661, §2702(a)(3), substituted "$200,000" for "20 percent of the amount specified by law as the maximum amount for a minor military construction project".

1985—Subsec. (a). Pub. L. 99–167, §809(1), inserted "an amount equal to 125 percent of".

Subsec. (c). Pub. L. 99–167, §809(2), substituted "The" for "Only funds authorized for minor construction projects may be used to accomplish unspecified minor construction projects, except that the".


Statutory Notes and Related Subsidiaries

Effective Date of 2022 Amendment

Pub. L. 117–263, div. B, title XXVIII, §2803(b), Dec. 23, 2022, 136 Stat. 2994, provided that: "Subsection (g) of section 2805 of title 10, United States Code, as added by subsection (a), shall apply with respect only to amounts appropriated after the date of the enactment of this Act [Dec. 23, 2022]."

Effective Date of 2021 Amendment

Amendment by Pub. L. 117–81 applicable as if included in the enactment of title XVIII of Pub. L. 116–283 as enacted, see section 1701(a)(2) of Pub. L. 117–81, set out in a note preceding section 3001 of this title and note below.

Amendment by section 1843(c) of Pub. L. 116–283 effective Jan. 1, 2022, with additional provisions for delayed implementation and applicability of existing law, see section 1801(d) of Pub. L. 116–283, set out as a note preceding section 3001 of this title.

Effective Date

For effective date and applicability of section, see section 12(a) of Pub. L. 97–214, set out as a note under section 2801 of this title.

Authority for Indo-Pacific Posture Unspecified Minor Military Construction Projects

Pub. L. 118–31, div. B, title XXVIII, §2810, Dec. 22, 2023, 137 Stat. 747, provided that:

"(a) Authority.—To support the posture of the Armed Forces in the United States Indo-Pacific Command area of operations, the Commander of the United States Indo-Pacific Command (in this section referred to as the 'Commander') may carry out unspecified minor military construction projects not otherwise authorized by law with an approved cost less than $15,000,000.

"(b) Scope of Project Authority.—A project carried out under this section may include—

"(1) the design, construction, development, conversion, extension, renovation, or repair of a facility, whether to satisfy temporary or permanent requirements; and

"(2) to the extent necessary, any acquisition of land subject to the limitations on real property acquisition of chapter 159 of title 10, United States Code.

"(c) Purposes.—A project carried out under this section shall be for the purpose of—

"(1) supporting the rotational deployments of the Armed Forces;

"(2) enhancing facility preparedness and military installation resilience (as defined in section 101(e)(8) of title 10, United States Code) in support of potential, planned, or anticipated defense activities; or

"(3) providing for prepositioning and storage of equipment and supplies.

"(d) Location of Projects.—A project carried out under this section must be located within the area of responsibility of the United States Indo-Pacific Command and at a military installation that includes a main operating base, cooperative security location, forward operating site, or contingency location for use by the Armed Forces.

"(e) Available Amounts.—In carrying out a project under this section, the Commander may use amounts appropriated for—

"(1) the INDOPACOM Military Construction Pilot Program fund (as specified in the funding table in section 4601 [Pub. L. 118–31, 137 Stat. 901]); and

"(2) operation and maintenance, not to exceed 200 percent of the amount specified in section 2805(c) of title 10, United States Code.

"(f) Notice to Congress.—

"(1) In general.—If the Commander decides to carry out a project under this section with a cost exceeding $2,000,000, the Commander shall submit a written notification to the congressional defense committees [Committees on Armed Services and Appropriations of the Senate and the House of Representatives] of that decision.

"(2) Relevant details.—A notice under paragraph (1) with respect to a project shall include relevant details and justification of the project, including the estimated cost, and may include a classified annex.

"(3) Timing.—A project under this section covered by paragraph (1) may not be carried out until the end of the 14-day period beginning on the date of receipt of the notification under such paragraph by the congressional defense committees.

"(g) Project Execution.—

"(1) Project supervision.—Subsections (a) and (b) of section 2851 of title 10, United States Code, shall not apply to projects carried out by the Commander under this section.

"(2) Application of chapter 169 of title 10, united states code.—When exercising the authority under subsection (a), the Commander shall, for purposes of chapter 169 of title 10, United States Code, be considered the Secretary concerned.

"(h) Annual Report.—Not later than December 31, 2024, and annually thereafter until the termination date in subsection (i), the Commander shall submit to the congressional defense committees a report containing a list of projects funded, lessons learned, and, subject to the concurrence of the Secretary of Defense, recommended adjustments to the authority under this section for the most recently ended fiscal year covered by the report.

"(i) Termination.—The authority to carry out a project under this section expires on March 31, 2029."

Temporary Increase of Amounts in Connection With Authority To Carry Out Unspecified Minor Military Construction

Pub. L. 117–263, div. B, title XXVIII, §2801, Dec. 23, 2022, 136 Stat. 2992, which increased amounts in connection with authority to carry out unspecified minor military construction projects for the period beginning on Dec. 23, 2022, and ending on Dec. 1, 2025, was repealed by Pub. L. 118–31, div. B, title XXVIII, §2802(e), Dec. 22, 2023, 137 Stat. 743.

No Application to Current Projects

Pub. L. 113–66, div. B, title XXVIII, §2801(b), Dec. 26, 2013, 127 Stat. 1006, provided that: "The amendments made by subsection (a) [amending this section] do not apply to any laboratory revitalization project for which the design phase has been completed as of the date of the enactment of this Act [Dec. 26, 2013]."

Relation to Other Authorities

Pub. L. 108–136, div. B, title XXVIII, §2808(e), Nov. 24, 2003, 117 Stat. 1724, which directed that the temporary authority provided by section 2808 of Pub. L. 108–136, and the limited authority provided by section 2805(c) of this title, to use appropriated funds available for operation and maintenance to carry out a construction project were the only authorities available to the Secretary of Defense and the Secretaries of the military departments to use appropriated funds available for operation and maintenance to carry out construction projects, was repealed by Pub. L. 117–263, div. B, title XXVIII, §2809(b)(2), Dec. 23, 2022, 136 Stat. 2996.

Department of Defense Laboratory Revitalization Demonstration Program

Pub. L. 104–106, div. B, title XXVIII, §2892, Feb. 10, 1996, 110 Stat. 590, as amended by Pub. L. 105–261, div. B, title XXVIII, §2871, Oct. 17, 1998, 112 Stat. 2225; Pub. L. 108–375, div. B, title XXVIII, §2891, Oct. 28, 2004, 118 Stat. 2154, provided that:

"(a) Program Authorized.—The Secretary of Defense may carry out a program (to be known as the 'Department of Defense Laboratory Revitalization Demonstration Program') for the revitalization of Department of Defense laboratories. Under the program, the Secretary may carry out minor military construction projects in accordance with subsection (b) and other applicable law to improve Department of Defense laboratories covered by the program.

"(b) Increased Maximum Amounts Applicable to Minor Construction Projects.—For purpose of any military construction project carried out under the program—

"(1) the amount provided in the second sentence of subsection (a)(1) of section 2805 of title 10, United States Code, shall be deemed to be $3,000,000;

"(2) the amount provided in subsection (b)(1) of such section shall be deemed to be $1,500,000; and

"(3) the amount provided in subsection (c)(1)(B) of such section shall be deemed to be $1,000,000.

"(c) Program Requirements.—(1) Not later than 30 days before commencing the program, the Secretary shall establish procedures for the review and approval of requests from Department of Defense laboratories for construction under the program.

"(2) The laboratories at which construction may be carried out under the program may not include Department of Defense laboratories that are contractor-owned.

"(d) Report.—Not later than February 1, 2003, the Secretary shall submit to Congress a report on the program. The report shall include the Secretary's conclusions and recommendation regarding the desirability of making the authority set forth under subsection (b) permanent.

"(e) Exclusivity of Program.—Nothing in this section may be construed to limit any other authority provided by law for any military construction project at a Department of Defense laboratory covered by the program.

"(f) Definitions.—In this section:

"(1) The term 'laboratory' includes—

"(A) a research, engineering, and development center;

"(B) a test and evaluation activity owned, funded, and operated by the Federal Government through the Department of Defense; and

"(C) a supporting facility of a laboratory.

"(2) The term 'supporting facility', with respect to a laboratory, means any building or structure that is used in support of research, development, test, and evaluation at the laboratory.

"(g) Expiration of Authority.—The Secretary may not commence a construction project under the program after September 30, 2005."

Initial Establishment of Certain Amounts Required To Be Specified by Law

Maximum amount of $1,000,000 for unspecified minor military construction project under this section during the period beginning Oct. 1, 1982, and ending on the date of the enactment of the Military Construction Authorization Act for fiscal year 1984 or Oct. 1, 1983, whichever is later, see section 11(1) of Pub. L. 97–214, set out as a note under section 2828 of this title.

§2806. Contributions for North Atlantic Treaty Organizations Security Investment

(a) Within amounts authorized by law for such purpose, the Secretary of Defense may make contributions for the United States share of the cost of multilateral programs for the acquisition and construction of military facilities and installations (including international military headquarters) and for related expenses for the collective defense of the North Atlantic Treaty Area.

(b) Funds may not be obligated or expended in connection with the North Atlantic Treaty Organization Security Investment program in any year unless such funds have been authorized by law for such program.

(c)(1) The Secretary of Defense may make contributions in excess of the amount appropriated for contribution under subsection (a) if the amount of the contribution in excess of that amount does not exceed 200 percent of the amount specified by section 2805(a) of this title as the maximum amount for a minor military construction project.

(2) If the Secretary determines that the amount appropriated for contribution under subsection (a) in any fiscal year must be exceeded by more than the amount authorized under paragraph (1), the Secretary may make contributions in excess of such amount, but not in excess of 125 percent of the amount appropriated, only after the end of the 14-day period beginning on the date on which the Secretary submits, in an electronic medium pursuant to section 480 of this title, to the appropriate committees of Congress notice of the increase, including the reasons for the increase and the source of the funds to be used for the increase.

(Added Pub. L. 97–214, §2(a), July 12, 1982, 96 Stat. 156; amended Pub. L. 97–321, title VIII, §805(b)(1), Oct. 15, 1982, 96 Stat. 1573; Pub. L. 99–661, div. B, title V, §2503(a), Nov. 14, 1986, 100 Stat. 4039; Pub. L. 100–26, §7(f)(1), Apr. 21, 1987, 101 Stat. 281; Pub. L. 102–190, div. B, title XXVIII, §2870(5), Dec. 5, 1991, 105 Stat. 1563; Pub. L. 104–201, div. B, title XXVIII, §2802(a), (c)(1), Sept. 23, 1996, 110 Stat. 2787; Pub. L. 111–84, div. B, title XXVIII, §2801(a)(3), Oct. 28, 2009, 123 Stat. 2660; Pub. L. 111–383, div. B, title XXVIII, §2803(b), Jan. 7, 2011, 124 Stat. 4459; Pub. L. 115–91, div. B, title XXVIII, §2801(a)(4), Dec. 12, 2017, 131 Stat. 1840.)


Editorial Notes

Amendments

2017—Subsec. (c)(1). Pub. L. 115–91, §2801(a)(4)(A), inserted "of Defense" after "The Secretary".

Subsec. (c)(2). Pub. L. 115–91, §2801(a)(4)(B), substituted ", only after the end of the 14-day period beginning on the date on which the Secretary submits, in an electronic medium pursuant to section 480 of this title, to the appropriate committees of Congress notice of the increase, including the reasons for the increase and the source of the funds to be used for the increase." for "(A) after submitting a report in writing to the appropriate committees of Congress on such increase, including a statement of the reasons for the increase and a statement of the source of the funds to be used for the increase, and (B) after a period of 21 days has elapsed from the date of receipt of the report or, if earlier, a period of 14 days has elapsed from the date on which a copy of the report is provided in an electronic medium pursuant to section 480 of this title."

2011—Subsec. (c)(2)(B). Pub. L. 111–383 inserted before period at end "or, if earlier, a period of 14 days has elapsed from the date on which a copy of the report is provided in an electronic medium pursuant to section 480 of this title".

2009—Subsec. (c)(1). Pub. L. 111–84 substituted "section 2805(a)" for "section 2805(a)(2)".

1996Pub. L. 104–201, §2802(c)(1), substituted "Organizations Security Investment" for "Organization Infrastructure" in section catchline.

Subsec. (b). Pub. L. 104–201, §2802(a), substituted "Security Investment program" for "Infrastructure program".

1991—Subsec. (c)(2)(B). Pub. L. 102–190 substituted "after" for "after either" and struck out before period at end "or after each such committee has indicated approval of the increased contribution".

1987—Subsec. (c)(1). Pub. L. 100–26 substituted "specified by section 2805(a)(2) of this title" for "specified by law".

1986—Subsec. (a). Pub. L. 99–661 inserted "and for related expenses" after "headquarters)".

1982Pub. L. 97–321 substituted "Infrastructure" for "infrastructure" in section catchline.


Statutory Notes and Related Subsidiaries

Change of Name

Pub. L. 104–201, div. B, title XXVIII, §2802(b), Sept. 23, 1996, 110 Stat. 2787, provided that: "Any reference to the North Atlantic Treaty Organization Infrastructure program in any Federal law, Executive order, regulation, delegation of authority, or document of or pertaining to the Department of Defense shall be deemed to refer to the North Atlantic Treaty Organization Security Investment program."

Effective Date of 1986 Amendment

Pub. L. 99–661, div. B, title V, §2503(b), Nov. 14, 1986, 100 Stat. 4039, provided that: "The amendment made by subsection (a) [amending this section] shall apply only with respect to contributions made with funds appropriated for fiscal years after fiscal year 1986."

Effective Date

For effective date and applicability of section, see section 12(a) of Pub. L. 97–214, set out as a note under section 2801 of this title.

Restriction on Certain Funding

Pub. L. 99–661, div. B, title V, §2504, Nov. 14, 1986, 100 Stat. 4039, prohibited Secretary of Defense from obligating or expending any funds after fiscal year 1987 with respect to NATO infrastructure program under this section until Secretary submitted to Committees on Armed Services of Senate and House (1) a comprehensive master plan for establishing adequate active defenses for air bases in Europe at which operations of United States aircraft are planned, sites in Europe used by United States for logistic support of NATO or for prepositioned overseas matériel configured to unit sets, and (2) a report containing a certification by Secretary that sufficient funds have been budgeted by Department of Defense in fiscal year 1988 five-year defense plan to meet objectives of such comprehensive master plan.

§2807. Architectural and engineering services and construction design

(a) Within amounts appropriated for military construction and military family housing, the Secretary concerned may obtain architectural and engineering services and may carry out construction design in connection with military construction projects, family housing projects, and projects undertaken in connection with the authority provided under section 2854 of this title that are not otherwise authorized by law. Amounts available for such purposes may be used for construction management of projects that are funded by foreign governments directly or through international organizations and for which elements of the armed forces of the United States are the primary user.

(b) In the case of architectural and engineering services and construction design to be undertaken under subsection (a) for which the estimated cost exceeds $1,000,000, the Secretary concerned shall notify the appropriate committees of Congress of the scope of the proposed project and the estimated cost of such services before the initial obligation of funds for such services. The Secretary may then obligate funds for such services only after the end of the 14-day period beginning on the date on which the notification is received by the committees in an electronic medium pursuant to section 480 of this title.

(c) If the Secretary concerned determines that the amount authorized for activities under subsection (a) in any fiscal year must be increased the Secretary may proceed with activities at such higher level only after the end of the 14-day period beginning on the date on which the Secretary submits, in an electronic medium pursuant to section 480 of this title, to the appropriate committees of Congress notice of the need for the increase, including the source of funds to be used for the increase.

(d) For architectural and engineering services and construction design related to military construction and family housing projects, the Secretaries of the military departments may incur obligations for contracts or portions of contracts using military construction and family housing appropriations from different fiscal years to the extent that those appropriations are available for obligation.

(Added Pub. L. 97–214, §2(a), July 12, 1982, 96 Stat. 156; amended Pub. L. 98–115, title VIII, §804, Oct. 11, 1983, 97 Stat. 785; Pub. L. 99–661, div. B, title VII, §§2702(b), 2712(a), Nov. 14, 1986, 100 Stat. 4040, 4041; Pub. L. 102–190, div. B, title XXVIII, §2870(6), Dec. 5, 1991, 105 Stat. 1563; Pub. L. 105–261, div. B, title XXVIII, §2801, Oct. 17, 1998, 112 Stat. 2202; Pub. L. 108–136, div. A, title X, §1031(a)(37), Nov. 24, 2003, 117 Stat. 1601; Pub. L. 115–91, div. B, title XXVIII, §2801(a)(5), Dec. 12, 2017, 131 Stat. 1841.)


Editorial Notes

Amendments

2017—Subsec. (b). Pub. L. 115–91, §2801(a)(5)(A), substituted "14-day period" for "21-day period" and struck out "or, if earlier, the end of the 14-day period beginning on the date on which a copy of the report is provided" after "received by the committees".

Subsec. (c). Pub. L. 115–91, §2801(a)(5)(B), substituted "only after the end of the 14-day period beginning on the date on which the Secretary submits, in an electronic medium pursuant to section 480 of this title, to the appropriate committees of Congress notice of the need for the increase, including the source of funds to be used for the increase." for "(1) after submitting a report in writing to the appropriate committees of Congress on such increase, including a statement of the reasons for the increase and a statement of the source of funds to be used for the increase, and (2) after a period of 21 days has elapsed from the date of receipt of the report or, if over sooner, a period of 14 days has elapsed from the date on which a copy of the report is provided in an electronic medium pursuant to section 480 of this title."

2003—Subsec. (b). Pub. L. 108–136, §1031(a)(37)(A), substituted "$1,000,000" for "$500,000", struck out "not less than 21 days" after "of such services", and inserted last sentence.

Subsec. (c)(2). Pub. L. 108–136, §1031(a)(37)(B), inserted before period at end "or, if over sooner, a period of 14 days has elapsed from the date on which a copy of the report is provided in an electronic medium pursuant to section 480 of this title".

1998—Subsec. (b). Pub. L. 105–261, §2801(a), substituted "$500,000" for "$300,000".

Subsec. (d). Pub. L. 105–261, §2801(b), substituted "architectural and engineering services and construction design" for "study, planning, design, architectural, and engineering services".

1991—Subsec. (c)(2). Pub. L. 102–190 substituted "after" for "after either" and struck out before period at end "or after each such committee has indicated approval of the increased level of activity".

1986—Subsec. (b). Pub. L. 99–661, §2702(b), substituted "$300,000" for "the maximum amount specified by law for the purposes of this section".

Subsec. (d). Pub. L. 99–661, §2712(a), added subsec. (d).

1983—Subsec. (a). Pub. L. 98–115 substituted "Within amounts appropriated for military construction and military family housing" for "Within amounts appropriated for such purposes" and inserted ", family housing projects, and projects undertaken in connection with the authority provided under section 2854 of this title that are" after "in connection with military construction projects".


Statutory Notes and Related Subsidiaries

Effective Date of 1986 Amendment

Pub. L. 99–661, div. B, title VII, §2712(b), Nov. 14, 1986, 100 Stat. 4041, provided that: "The amendment made by subsection (a) [amending this section] shall apply only to funds appropriated for fiscal years after fiscal year 1985."

Effective Date

For effective date and applicability of section, see section 12(a) of Pub. L. 97–214, set out as a note under section 2801 of this title.

Architectural and Engineering Services and Construction Design Contracts for Military Construction Projects

Pub. L. 98–212, title VII, §796, Dec. 8, 1983, 97 Stat. 1455, provided that: "No funds appropriated for the Departments of Defense, Army, Navy, or the Air Force shall be obligated by their respective Secretaries for architectural and engineering services and construction design contracts for Military Construction projects in the amount of $85,000 and over, unless competition for such contracts is open to all firms regardless of size in accordance with 40 U.S.C. §541, et seq. [now chapter 11 of Title 40, Public Buildings, Property, and Works.]"

Small Business Set-Aside for Architectural and Engineering Services and Construction Design

Pub. L. 98–115, title VIII, §806, Oct. 11, 1983, 97 Stat. 786, provided that:

"(a) The Secretary of Defense shall conduct a comprehensive review of current policies and practices of the Department of Defense with regard to the award of contracts for architectural and engineering services and construction design for military construction projects. The Secretary shall conduct such review with a view to determining whether current policies and practices of the Department of Defense result in a reasonable distribution of such contracts to firms of all sizes throughout the architect-engineer community.

"(b) Upon the completion of such review, the Secretary shall modify current policies and practices of the Department to the extent necessary to ensure—

"(1) that small business concerns (as defined in section 3 of the Small Business Act [15 U.S.C. 632]) are assured of a reasonable share of such contracts; and

"(2) that large architect-engineer firms are not precluded from competing for such contracts when the estimated amount of such contracts is greater than a reasonable threshold amount prescribed by the Secretary.

"(c) Not later than March 1, 1984, the Secretary shall submit to the appropriate committees of Congress a written report on the results of the review required by subsection (a) and on any changes made to current policies and practices as required by subsection (b).

"(d) For the purposes of this section:

"(1) The term 'reasonable share' means an appropriate percentage share of all contracts referred to in subsection (a) as determined by the Secretary of Defense after consultation with the Admininstrator [sic] of the Small Business Administration and representatives of the architect-engineer community.

"(2) The term 'reasonable threshold amount' means an appropriate estimated contract dollar amount determined by the Secretary of Defense after consultation with the Administrator of the Small Business Administration and representatives of the architect-engineer community."

Initial Establishment of Certain Amounts Required To Be Specified by Law

Amounts of $300,000 or more for contracts for architectural and engineering services or construction design subject to the reporting requirement under this section during the period beginning on Oct. 1, 1982, and ending on the date of the Military Construction Authorization Act for fiscal year 1984 or Oct. 1, 1983, whichever is later, see section 11(2) of Pub. L. 97–214, set out as a note under section 2828 of this title.

§2808. Construction authority in the event of a declaration of war or national emergency

(a) Construction Authorized.—In the event of a declaration of war or the declaration by the President of a national emergency in accordance with the National Emergencies Act (50 U.S.C. 1601 et seq.) that requires use of the armed forces, the Secretary of Defense, without regard to any other provision of law, may undertake military construction projects, and may authorize the Secretaries of the military departments to undertake military construction projects, not otherwise authorized by law that are necessary to support such use of the armed forces.

(b) Conditions on Sources of Funds.—A military construction project to be undertaken using the construction authority described in subsection (a) may be undertaken only within the total amount of funds that have been appropriated for military construction, excluding funds appropriated for family housing, that—

(1) remain unobligated as of the date on which the first contract would be entered into in support of the national emergency declaration described in subsection (a); and

(2) are available because the military construction project for which the funds were appropriated—

(A) has been canceled; or

(B) has reduced costs as a result of project modifications or other cost savings.


(c) Limitation on Amount of Funds Available for National Emergency.—(1) Except as provided in paragraph (2), in the event of a declaration by the President of a national emergency in which the construction authority described in subsection (a) is used, the total cost of all military construction projects undertaken using that authority during the national emergency may not exceed $500,000,000.

(2) In the event of a national emergency declaration in which the construction authority described in subsection (a) will be used only within the United States, the total cost of all military construction projects undertaken using that authority during the national emergency may not exceed $100,000,000.

(d) Waiver of Other Provisions of Law in Event of National Emergency.—In the event of a declaration by the President of a national emergency in which the construction authority described in subsection (a) is used, the authority provided by such subsection to waive or disregard another provision of law that would otherwise apply to a military construction project authorized by this section may be used only if—

(1) such other provision of law does not provide a means by which compliance with the requirements of the law may be waived, modified, or expedited; and

(2) the Secretary of Defense determines that the nature of the national emergency necessitates the noncompliance with the requirements of the law.


(e) Notification Requirement.—(1)When a decision is made to undertake military construction projects authorized by this section, the Secretary of Defense shall notify, in an electronic medium pursuant to section 480 of this title, the appropriate committees of Congress of the following:

(A) The reasons for the decision to use the construction authority described in subsection (a), including, in the event of a declaration by the President of a national emergency, the reasons why use of the armed forces is required in response to the declared national emergency.

(B) The construction projects to be undertaken using the construction authority described in subsection (a), including, in the event of a declaration by the President of a national emergency, an explanation of how each construction project directly supports the immediate security, logistical, or short-term housing and ancillary supporting facility needs of the members of the armed forces used in the national emergency.

(C) The estimated cost of the construction projects to be undertaken using the construction authority described in subsection (a), including the cost of any real estate action pertaining to the construction projects, and certification of compliance with the funding conditions imposed by subsections (b) and (c).

(D) Any determination made pursuant to subsection (d)(2) to waive or disregard another provision of law to undertake any construction project using the construction authority described in subsection (a).

(E) The military construction projects, including any ancillary supporting facility projects, whose cancellation, modification, or other cost savings result in funds being available to undertake construction projects using the construction authority described in subsection (a) and the possible impact of the cancellation or modification of such military construction projects on military readiness and the quality of life of members of the armed forces and their dependents.


(2) In the event of a declaration by the President of a national emergency in which the construction authority described in subsection (a) is used, a construction project to be undertaken using such construction authority may be carried out only after the end of the five-day period beginning on the date the notification required by paragraph (1) is received by the congressional defense committees.

(f) Termination of Authority.—The authority described in subsection (a) shall terminate with respect to any war or national emergency at the end of the war or national emergency.

(Added Pub. L. 97–214, §2(a), July 12, 1982, 96 Stat. 157; amended Pub. L. 115–91, div. B, title XXVIII, §2801(a)(6), Dec. 12, 2017, 131 Stat. 1841; Pub. L. 116–283, div. B, title XXVIII, §2801(a)–(e), Jan. 1, 2021, 134 Stat. 4317–4319.)


Editorial Notes

References in Text

The National Emergencies Act (50 U.S.C. 1601 et seq.), referred to in subsec. (a), is Pub. L. 94–412, Sept. 14, 1976, 90 Stat. 1255, as amended, which is classified principally to chapter 34 (§1601 et seq.) of Title 50, War and National Defense. For complete classification of this Act to the Code, see Short Title note set out under section 1601 of Title 50 and Tables.

Prior Provisions

Provisions similar to those in this section were contained in Pub. L. 97–99, title IX, §903, Dec. 23, 1981, 95 Stat. 1382, which was set out as a note under section 140 [now 127] of this title, prior to repeal by Pub. L. 97–214, §7(18).

Amendments

2021—Subsec. (a). Pub. L. 116–283, §2801(b), (e)(1), inserted heading and struck out "Such projects may be undertaken only within the total amount of funds that have been appropriated for military construction, including funds appropriated for family housing, that have not been obligated." at end.

Subsec. (b). Pub. L. 116–283, §2801(b), added subsec. (b). Former subsec. (b) redesignated (e).

Subsec. (c). Pub. L. 116–283, §2801(a)(2), added subsec. (c). Former subsec. (c) redesignated (f).

Subsec. (d). Pub. L. 116–283, §2801(c), added subsec. (d).

Subsec. (e). Pub. L. 116–283, §2801(a)(1), (d), (e)(2), redesignated subsec. (b) as (e), inserted heading and par. (1) designation before "When a decision", substituted "of the following:" and subpars. (A) to (E) for "of the decision and of the estimated cost of the construction projects, including the cost of any real estate action pertaining to those construction projects.", and added par. (2).

Subsec. (f). Pub. L. 116–283, §2801(a)(1), (e)(3), redesignated subsec. (c) as (f) and inserted heading.

2017—Subsec. (b). Pub. L. 115–91 inserted ", in an electronic medium pursuant to section 480 of this title," after "shall notify".


Statutory Notes and Related Subsidiaries

Effective Date

For effective date and applicability of section, see section 12(a) of Pub. L. 97–214, set out as a note under section 2801 of this title.

Exception for Pandemic Mitigation and Response Projects

Pub. L. 116–283, div. B, title XXVIII, §2801(f), Jan. 1, 2021, 134 Stat. 4319, provided that: "Subsections (b), (c), (d) of section 2808 of title 10, United States Code, as added by this section, shall not apply to a military construction project commenced under the authority of subsection (a) of such section 2808 during the emergency period described in section 1135(g)(1)(B) of the Social Security Act (42 U.S.C. 1320b–5(g)(1)(B)) if the Secretary of Defense determines that the military construction project will directly support pandemic mitigation and response efforts of health care providers or support members of the Armed Forces directly participating in such pandemic mitigation and response efforts. Subsection (e) of section 2808 of title 10, United States Code, as redesignated by subsection (a)(1) and amended by subsection (d) of this section, shall still apply to any such military construction project."


Executive Documents

Executive Order No. 12734

Ex. Ord. No. 12734, Nov. 14, 1990, 55 F.R. 48099, which related to national emergency construction authority, was revoked by Ex. Ord. No. 13350, July 29, 2004, 69 F.R. 46055, listed in a table under section 1701 of Title 50, War and National Defense.

Ex. Ord. No. 13235. National Emergency Construction Authority

Ex. Ord. No. 13235, Nov. 16, 2001, 66 F.R. 58343, provided:

By the authority vested in me as President by the Constitution and the laws of the United States of America, including the National Emergencies Act (50 U.S.C. 1601 et seq.), and section 301 of title 3, United States Code, I declared a national emergency that requires the use of the Armed Forces of the United States, by Proclamation 7463 of September 14, 2001 [50 U.S.C. 1621 note], because of the terrorist attacks on the World Trade Center and the Pentagon, and because of the continuing and immediate threat to the national security of the United States of further terrorist attacks. To provide additional authority to the Department of Defense to respond to that threat, and in accordance with section 301 of the National Emergencies Act (50 U.S.C. 1631), I hereby order that the emergency construction authority at 10 U.S.C. 2808 is invoked and made available in accordance with its terms to the Secretary of Defense and, at the discretion of the Secretary of Defense, to the Secretaries of the military departments.

George W. Bush.      

§2809. Long-term facilities contracts for certain activities and services

(a) Submission and Authorization of Proposed Projects.—The Secretary concerned may enter into a contract for the procurement of services in connection with the construction, management, and operation of a facility on or near a military installation for the provision of an activity or service described in subsection (b) if—

(1) the Secretary concerned has identified the proposed project for that facility in the budget material submitted to Congress by the Secretary of Defense in connection with the budget submitted pursuant to section 1105 of title 31 for the fiscal year in which the contract is proposed to be awarded;

(2) the Secretary concerned has determined that the services to be provided at that facility can be more economically provided through the use of a long-term contract than through the use of conventional means; and

(3) the project has been authorized by law.


(b) Authorized Purposes of Contract.—The activities and services referred to in subsection (a) are as follows:

(1) Child care services.

(2) Utilities, including potable and waste water treatment services.

(3) Depot supply activities.

(4) Troop housing.

(5) Transient quarters.

(6) Hospital or medical facilities.

(7) Other logistic and administrative services, other than depot maintenance.


(c) Conditions on Obligation of Funds.—A contract entered into for a project pursuant to subsection (a) shall include the following provisions:

(1) A statement that the obligation of the United States to make payments under the contract in any fiscal year is subject to appropriations being provided specifically for that fiscal year and specifically for that project.

(2) A commitment to obligate the necessary amount for each fiscal year covered by the contract when and to the extent that funds are appropriated for that project for that fiscal year.

(3) A statement that such a commitment given under the authority of this section does not constitute an obligation of the United States.


(d) Competitive Procedures.—Each contract entered into under this section shall be awarded through the use of competitive procedures as provided in chapter 137 1 of this title. In accordance with such procedures, the Secretary concerned shall solicit bids or proposals for a contract for each project that has been authorized by law.

(e) Term of Contract.—A contract under this section may be for any period not in excess of 32 years, excluding the period for construction.

(f) Notice and Wait Requirements.—The Secretary concerned may enter into a contract under this section only after the end of the 14-day period beginning on the date on which the Secretary submits, in an electronic medium pursuant to section 480 of this title, to the appropriate committees of Congress a justification of the need for the facility covered by the proposed contract, including an economic analysis (based upon accepted life cycle costing procedures) which demonstrates that the proposed contract is cost effective when compared with alternative means of furnishing the same facility.

(Added Pub. L. 99–167, title VIII, §811(a), Dec. 3, 1985, 99 Stat. 990; amended Pub. L. 99–661, div. A, title XIII, §1343(a)(20), div. B, title VII, §2711, Nov. 14, 1986, 100 Stat. 3994, 4041; Pub. L. 100–180, div. B, subdiv. 3, title I, §2302(a), (b), Dec. 4, 1987, 101 Stat. 1215; Pub. L. 100–456, div. B, title XXVIII, §2801, Sept. 29, 1988, 102 Stat. 2115; Pub. L. 101–189, div. B, title XXVIII, §2803, Nov. 29, 1989, 103 Stat. 1647; Pub. L. 102–190, div. B, title XXVIII, §2805(a)(1), Dec. 5, 1991, 105 Stat. 1537; Pub. L. 108–136, div. A, title X, §1031(a)(38), Nov. 24, 2003, 117 Stat. 1601; Pub. L. 115–91, div. B, title XXVIII, §2801(a)(7), Dec. 12, 2017, 131 Stat. 1841.)


Editorial Notes

References in Text

Chapter 137 of this title, referred to in subsec. (d), was repealed by Pub. L. 116–283, div. A, title XVIII, §1881(a), Jan. 1, 2021, 134 Stat. 4293, effective Jan. 1, 2022, in conjunction with the transfer and reorganization of acquisition provisions in this title by Pub. L. 116–283, div. A, title XVIII, Jan. 1, 2022, 134 Stat. 4149. For definition of "chapter 137 legacy provisions", see section 3016 of this title.

Amendments

2017—Subsec. (f). Pub. L. 115–91 added subsec. (f) and struck out former subsec. (f) which related to written or electronic notice and wait requirements for a contract.

2003—Subsec. (f)(2). Pub. L. 108–136 struck out "calendar" after "21" and inserted before period at end "or, if over sooner, a period of 14 days has expired following the date on which a copy of the justification and economic analysis are provided in an electronic medium pursuant to section 480 of this title".

1991Pub. L. 102–190 substituted section catchline for one which read "Test of long-term facilities contracts" and amended text generally, substituting present provisions for provisions authorizing contracts for construction, management, and operation of facilities on or near military installations for the provision of certain enumerated activities or services, setting out procedures, terms, and other limits for such contracts, providing that no more than 5 contracts may be entered into under this section other than contracts for child care centers, and providing that authority to enter into such contracts was to expire on Sept. 30, 1991.

1989—Subsec. (a)(1)(B)(ii). Pub. L. 101–189, §2803(1), substituted "Utilities, including potable" for "Potable".

Subsec. (b). Pub. L. 101–189, §2803(2), substituted "activities and services described in clause (i) or (ii) of subsection (a)(1)(B)" for "child care centers".

Subsec. (c). Pub. L. 101–189, §2803(3), substituted "1991" for "1989".

1988—Subsec. (a)(3). Pub. L. 100–456 substituted "32" for "20".

1987—Subsec. (a)(1)(B)(vi), (vii). Pub. L. 100–180, §2302(a), added cl. (vi) and redesignated former cl. (vi) as (vii).

Subsec. (c). Pub. L. 100–180, §2302(b), substituted "1989" for "1987".

1986—Subsec. (a)(1). Pub. L. 99–661, §2711, amended par. (1) generally. Prior to amendment, par. (1) read as follows: "The Secretary concerned may enter into a contract for the construction, management, and operation of a facility on or near a military installation in the United States for the provision of child care services, waste water treatment, or depot supply activities in a case in which the Secretary concerned determines that the facility can be more efficiently and more economically provided under a long-term contract than by other appropriate means."

Pub. L. 99–661, §1343(a)(20)(A), substituted "a contract" for "contracts", "a facility" for "facilities", "a military installation" for "military installations", "a case" for "cases", "facility" for "facilities", and "a long-term contract" for "long-term contracts" and inserted a comma after "waste water treatment".

Subsec. (a)(2). Pub. L. 99–661, §1343(a)(20)(B), substituted "this section" for "subsection (a)".

Subsec. (a)(3). Pub. L. 99–661, §1343(a)(20)(C), substituted "20" for "twenty".

Subsec. (a)(4)(A). Pub. L. 99–661, §1343(a)(20)(D), struck out "the" before "Congress".

Subsec. (b). Pub. L. 99–661, §1343(a)(20)(E), struck out "the authority of subsection (a) of" after "under".


Statutory Notes and Related Subsidiaries

Effective Date of 1991 Amendment

Pub. L. 102–190, div B, title XXVIII, §2805(b), Dec. 5, 1991, 105 Stat. 1538, provided that: "Section 2809 of title 10, United States Code, as amended by subsection (a), shall apply with respect to contracts entered into under that section on or after the date of the enactment of this Act [Dec. 5, 1991]."

Effective Date of 1988 Amendment

Amendment by Pub. L. 100–456 effective Oct. 1, 1988, see section 2702 of Pub. L. 100–456, set out as a note under section 2391 of this title.

Demonstration Program on Reduction in Long-Term Facility Maintenance Costs

Pub. L. 107–107, div. B, title XXVIII, §2814, Dec. 28, 2001, 115 Stat. 1310, as amended by Pub. L. 107–314, div. B, title XXVIII, §2813(a)–(d)(1), Dec. 2, 2002, 116 Stat. 2709, 2710, provided that:

"(a) Authority To Carry Out Program.—The Secretary of Defense or the Secretary of a military department may conduct a demonstration program to assess the feasibility and desirability of including facility maintenance requirements in construction contracts for military construction projects for the purpose of determining whether such requirements facilitate reductions in the long-term facility maintenance costs of the military departments.

"(b) Contracts.—(1) Not more than 12 contracts per military department may contain requirements referred to in subsection (a) for the purpose of the demonstration program.

"(2) The demonstration program may only cover contracts entered into on or after the date of the enactment of the Bob Stump National Defense Authorization Act for Fiscal Year 2003 [Pub. L. 107–314, approved Dec. 2, 2002], except that the Secretary of the Army shall treat any contract containing requirements referred to in subsection (a) that was entered into under the authority in such subsection between that date and December 28, 2001, as a contract for the purpose of the demonstration program.

"(c) Effective Period of Requirements.—The effective period of a requirement referred to in subsection (a) that is included in a contract for the purpose of the demonstration program may not exceed five years.

"(d) Reporting Requirements.—Not later than January 31, 2005, the Secretary of Defense shall submit to Congress a report on the demonstration program, including the following:

"(1) A description of all contracts that contain requirements referred to in subsection (a) for the purpose of the demonstration program.

"(2) An evaluation of the demonstration program and a description of the experience of the Secretary with respect to such contracts.

"(3) Any recommendations, including recommendations for the termination, continuation, or expansion of the demonstration program, that the Secretary considers appropriate.

"(e) Expiration.—The authority under subsection (a) to include requirements referred to in that subsection in contracts under the demonstration program shall expire on September 30, 2006.

"(f) Funding.—Amounts authorized to be appropriated for the military departments or defense-wide for a fiscal year for military construction shall be available for the demonstration program under this section in such fiscal year."

[Pub. L. 107–314, div. B, title XXVIII, §2813(d)(2), Dec. 2, 2002, 116 Stat. 2710, provided that: "The amendment made by paragraph (1) [amending section 2814(f) of Pub. L. 107–107, set out above] shall not affect the availability for the purpose of the demonstration program under section 2814 of the Military Construction Authorization Act for Fiscal Year 2002, as amended by this section, of any amounts authorized to be appropriated before the date of the enactment of this Act [Dec. 2, 2002] for the Army for military construction that have been obligated for the demonstration program, but not expended, as of that date."]

Report

Pub. L. 100–180, div. B, subdiv. 3, title I, §2302(c), Dec. 4, 1987, 101 Stat. 1215, directed each Secretary who has entered into a contract under this section to submit a report to Committees on Armed Services of Senate and House of Representatives by Feb. 15, 1989, containing date and duration of, other party to, and nature of activities carried out under each such contract, and recommendations, and reasons therefor, concerning whether authority to enter into contracts under this section should be extended.

1 See References in Text note below.

§2810. Military construction projects for innovation, research, development, test, and evaluation

(a) Project Authorization Required.—The Secretary of Defense may carry out such military construction projects for innovation, research, development, test, and evaluation as are authorized by law, using funds appropriated or otherwise made available for that purpose.

(b) Submission of Project Proposals.—As part of the defense budget materials for each fiscal year, the Secretary of Defense shall include the following information for each military construction project covered by subsection (a):

(1) The project title.

(2) The location of the project.

(3) A brief description of the scope of work.

(4) A completed Department of Defense Form 1391 budget justification that includes the original project cost estimate.

(5) A current working cost estimate, if different that the cost estimate contained in such Form 1391.

(6) Such other information as the Secretary considers appropriate.


(c) Budget Justification Display.—The Secretary of Defense shall include with the defense budget materials for each fiscal year a consolidated budget justification display that individually identifies each military construction project covered by subsection (a) and the amount requested for such project for such fiscal year.

(d) Application to Military Construction Projects.—This section shall apply to military construction projects covered by subsection (a) for which a Department of Defense Form 1391 is submitted to the appropriate committees of Congress in connection with the budget of the Department of Defense for fiscal year 2023 and thereafter.

(Added Pub. L. 117–263, div. B, title XXVIII, §2805(a), Dec. 23, 2022, 136 Stat. 2994.)


Editorial Notes

Prior Provisions

A prior section 2810, added Pub. L. 99–499, title II, §211(b)(1), Oct. 17, 1986, 100 Stat. 1725, related to military construction projects for environmental response actions, prior to repeal by Pub. L. 107–314, div. A, title III, §313(b), Dec. 2, 2002, 116 Stat. 2507.

§2811. Repair of facilities

(a) Repairs Using Operations and Maintenance Funds.—Using funds available to the Secretary concerned for operation and maintenance, the Secretary concerned may carry out repair projects for an entire single-purpose facility or one or more functional areas of a multipurpose facility.

(b) Approval Required for Major Repairs.—A repair project costing more than $7,500,000 may not be carried out under this section unless approved in advance by the Secretary concerned. In determining the total cost of a repair project, the Secretary shall include all phases of a multi-year repair project to a single facility. In considering a repair project for approval, the Secretary shall ensure that the project is consistent with force structure plans, that repair of the facility is more cost effective than replacement, and that the project is an appropriate use of operation and maintenance funds.

(c) Prohibition on New Construction or Additions.—Construction of new facilities or additions to existing facilities may not be carried out under the authority of this section.

(d) Congressional Notification.—When a decision is made to carry out a repair project under this section with an estimated cost in excess of $7,500,000, the Secretary concerned shall submit, in an electronic medium pursuant to section 480 of this title, to the appropriate committees of Congress a report containing—

(1) the justification for the repair project and the current estimate of the cost of the project, including, in the case of a multi-year repair project to a single facility, the total cost of all phases of the project;

(2) if the current estimate of the cost of the repair project exceeds 75 percent of the estimated cost of a military construction project to replace the facility, an explanation of the reasons why replacement of the facility is not in the best interest of the Government; and

(3) a description of the elements of military construction, including the elements specified in section 2802(b) of this title, incorporated into the repair project.


(e) Repair Project Defined.—In this section, the term "repair project" means a project—

(1) to restore a real property facility, system, or component to such a condition that it may effectively be used for its designated functional purpose; or

(2) to convert a real property facility, system, or component to a new functional purpose without increasing its external dimensions.

(Added Pub. L. 99–661, div. A, title III, §315(a), Nov. 14, 1986, 100 Stat. 3854, §2810; renumbered §2811, Pub. L. 100–26, §7(e)(3), Apr. 21, 1987, 101 Stat. 281; amended Pub. L. 103–337, div. B, title XXVIII, §2801(a), Oct. 5, 1994, 108 Stat. 3050; Pub. L. 105–85, div. B, title XXVIII, §2802, Nov. 18, 1997, 111 Stat. 1990; Pub. L. 108–375, div. B, title XXVIII, §2801, Oct. 28, 2004, 118 Stat. 2119; Pub. L. 111–84, div. B, title XXVIII, §2802, Oct. 28, 2009, 123 Stat. 2661; Pub. L. 114–328, div. B, title XXVIII, §2802, Dec. 23, 2016, 130 Stat. 2712; Pub. L. 115–91, div. B, title XXVIII, §2801(a)(8), Dec. 12, 2017, 131 Stat. 1841.)


Editorial Notes

Amendments

2017—Subsec. (d). Pub. L. 115–91 inserted ", in an electronic medium pursuant to section 480 of this title," after "shall submit" in introductory provisions.

2016—Subsec. (e). Pub. L. 114–328 amended subsec. (e) generally. Prior to amendment, text read as follows: "In this section, the term 'repair project' means a project to restore a real property facility, system, or component to such a condition that it may effectively be used for its designated functional purpose."

2009—Subsec. (d)(2), (3). Pub. L. 111–84 added pars. (2) and (3) and struck out former par. (2) which read as follows: "the justification for carrying out the project under this section."

2004—Subsec. (b). Pub. L. 108–375, §2801(a), substituted "$7,500,000" for "$5,000,000".

Subsec. (d). Pub. L. 108–375, §2801(b), substituted "$7,500,000" for "$10,000,000" in introductory provisions.

Subsec. (d)(1). Pub. L. 108–375, §2801(c), inserted before semicolon ", including, in the case of a multi-year repair project to a single facility, the total cost of all phases of the project".

1997—Subsecs. (d), (e). Pub. L. 105–85 added subsecs. (d) and (e).

1994Pub. L. 103–337 substituted "Repair" for "Renovation" in section catchline and amended text generally. Prior to amendment, text read as follows:

"(a) The Secretary concerned may carry out renovation projects that combine maintenance, repair, and minor construction projects for an entire single-purpose facility, or one or more functional areas of a multipurpose facility, using funds available for operations and maintenance.

"(b) The amount obligated on such a renovation project may not exceed the maximum amount specified by law for a minor construction project under section 2805 of this title.

"(c) Construction of new facilities or additions to existing facilities may not be carried out under the authority of this section."

§2812. Lease-purchase of facilities

(a)(1) The Secretary concerned may enter into an agreement with a private contractor for the lease of a facility of the kind specified in paragraph (2) if the facility is provided at the expense of the contractor on a military installation under the jurisdiction of the Department of Defense.

(2) The facilities that may be leased pursuant to paragraph (1) are as follows:

(A) Administrative office facilities.

(B) Troop housing facilities.

(C) Energy production facilities.

(D) Utilities, including potable and waste water treatment facilities.

(E) Hospital and medical facilities.

(F) Transient quarters.

(G) Depot or storage facilities.

(H) Child care centers.

(I) Classroom and laboratories.


(b) Leases entered into under subsection (a)—

(1) may not exceed a term of 32 years;

(2) shall provide that, at the end of the term of the lease, title to the leased facility shall vest in the United States; and

(3) shall include such other terms and conditions as the Secretary concerned determines are necessary or desirable to protect the interests of the United States.


(c)(1) The Secretary concerned may enter into a lease under this section only after the end of the 14-day period beginning on the date on which the Secretary submits, in an electronic medium pursuant to section 480 of this title, to the appropriate committees of Congress a justification of the need for the facility covered by the proposed lease, including an economic analysis (based upon accepted life-cycle costing procedures) that demonstrates the cost effectiveness of the proposed lease compared with a military construction project for the same facility.

(2) Each Secretary concerned may, under this section, enter into—

(A) not more than three leases in fiscal year 1990; and

(B) not more than five leases in each of the fiscal years 1991 and 1992.


(d) Each lease entered into under this section shall include a provision that the obligation of the United States to make payments under the lease in any fiscal year is subject to the availability of appropriations for that purpose.

(Added Pub. L. 101–189, div. B, title XXVIII, §2809(a), Nov. 29, 1989, 103 Stat. 1649; amended Pub. L. 101–510, div. B, title XXVIII, §2864, Nov. 5, 1990, 104 Stat. 1806; Pub. L. 108–136, div. A, title X, §1031(a)(39), Nov. 24, 2003, 117 Stat. 1601; Pub. L. 115–91, div. B, title XXVIII, §2801(a)(9), Dec. 12, 2017, 131 Stat. 1841.)


Editorial Notes

Amendments

2017—Subsec. (c)(1). Pub. L. 115–91 added par. (1) and struck out former par. (1) which set out justification, economic analysis, and wait requirements for entering into a lease.

2003—Subsec. (c)(1)(B). Pub. L. 108–136 inserted before period at end "or, if over sooner, a period of 14 days has expired following the date on which a copy of the justification and economic analysis are provided in an electronic medium pursuant to section 480 of this title".

1990—Subsec. (a)(2)(I). Pub. L. 101–510 added subpar. (I).

§2813. Acquisition of existing facilities in lieu of authorized construction

(a) Acquisition Authority.—Using funds appropriated for a military construction project authorized by law for a military installation, the Secretary of the military department concerned may acquire an existing facility (including the real property on which the facility is located) at or near the military installation instead of carrying out the authorized military construction project if the Secretary determines that—

(1) the acquisition of the facility satisfies the requirements of the military department concerned for the authorized military construction project; and

(2) it is in the best interests of the United States to acquire the facility instead of carrying out the authorized military construction project.


(b) Modification or Conversion of Acquired Facility.—(1) As part of the acquisition of an existing facility under subsection (a), the Secretary of the military department concerned may carry out such modifications, repairs, or conversions of the facility as the Secretary considers to be necessary so that the facility satisfies the requirements for which the military construction project was authorized.

(2) The costs of anticipated modifications, repairs, or conversions under paragraph (1) are required to remain within the authorized amount of the military construction project. The Secretary concerned shall consider such costs in determining whether the acquisition of an existing facility is—

(A) more cost effective than carrying out the authorized military construction project; and

(B) in the best interests of the United States.


(c) Notice and Wait Requirements.—A contract may not be entered into for the acquisition of a facility under subsection (a) until the Secretary concerned notifies the appropriate committees of Congress of the determination to acquire an existing facility instead of carrying out the authorized military construction project. The notification shall include the reasons for acquiring the facility. After the notification is transmitted, the Secretary may then enter into the contract only after the end of the 14-day period beginning on the date on which the notification is received by the committees in an electronic medium pursuant to section 480 of this title.

(Added Pub. L. 103–160, div. B, title XXVIII, §2805(a)(1), Nov. 30, 1993, 107 Stat. 1886; amended Pub. L. 104–106, div. A, title XV, §1502(a)(25), Feb. 10, 1996, 110 Stat. 506; Pub. L. 108–136, div. A, title X, §1031(a)(40), Nov. 24, 2003, 117 Stat. 1601; Pub. L. 109–163, div. B, title XXVIII, §2801(b), Jan. 6, 2006, 119 Stat. 3504; Pub. L. 115–91, div. B, title XXVIII, §2801(a)(10), Dec. 12, 2017, 131 Stat. 1841.)


Editorial Notes

Amendments

2017—Subsec. (c). Pub. L. 115–91 substituted "notifies the appropriate committees of Congress" for "transmits to the appropriate committees of Congress a written notification" and "14-day period" for "21-day period" and struck out "or, if earlier, the end of the 14-day period beginning on the date on which a copy of the report is provided" after "received by the committees".

2006—Subsec. (c). Pub. L. 109–163 substituted "21-day period" for "30-day period" and "14-day period" for "21-day period".

2003—Subsec. (c). Pub. L. 108–136 struck out "the end of the 30-day period beginning on the date" after "until" and inserted last sentence.

1996—Subsec. (c). Pub. L. 104–106 substituted "appropriate committees of Congress" for "Committees on Armed Services and the Committees on Appropriations of the Senate and House of Representatives".


Statutory Notes and Related Subsidiaries

Effective Date

Pub. L. 103–160, div. B, title XXVIII, §2805(b), Nov. 30, 1993, 107 Stat. 1887, provided that: "Section 2813 of title 10, United States Code, as added by subsection (a), shall apply with respect to military construction projects authorized on or after the date of the enactment of this Act [Nov. 30, 1993]."

§2814. Special authority for development of Ford Island, Hawaii

(a) In General.—(1) Subject to paragraph (2), the Secretary of the Navy may exercise any authority or combination of authorities in this section for the purpose of developing or facilitating the development of Ford Island, Hawaii, to the extent that the Secretary determines the development is compatible with the mission of the Navy.

(2) The Secretary of the Navy may not exercise any authority under this section until—

(A) the Secretary submits to the appropriate committees of Congress a master plan for the development of Ford Island, Hawaii; and

(B) a period of 30 calendar days has elapsed following the date on which the notification is received by those committees.


(b) Conveyance Authority.—(1) The Secretary of the Navy may convey to any public or private person or entity all right, title, and interest of the United States in and to any real property (including any improvements thereon) or personal property under the jurisdiction of the Secretary in the State of Hawaii that the Secretary determines—

(A) is excess to the needs of the Navy and all of the other armed forces; and

(B) will promote the purpose of this section.


(2) A conveyance under this subsection may include such terms and conditions as the Secretary considers appropriate to protect the interests of the United States.

(c) Lease Authority.—(1) The Secretary of the Navy may lease to any public or private person or entity any real property or personal property under the jurisdiction of the Secretary in the State of Hawaii that the Secretary determines—

(A) is not needed for current operations of the Navy and all of the other armed forces; and

(B) will promote the purpose of this section.


(2) A lease under this subsection shall be subject to section 2667(b)(1) of this title and may include such other terms as the Secretary considers appropriate to protect the interests of the United States.

(3) A lease of real property under this subsection may provide that, upon termination of the lease term, the lessee shall have the right of first refusal to acquire the real property covered by the lease if the property is then conveyed under subsection (b).

(4)(A) The Secretary may provide property support services to or for real property leased under this subsection.

(B) To the extent provided in appropriations Acts, any payment made to the Secretary for services provided under this paragraph shall be credited to the appropriation, account, or fund from which the cost of providing the services was paid.

(d) Acquisition of Leasehold Interest by Secretary.—(1) The Secretary of the Navy may acquire a leasehold interest in any facility constructed under subsection (f) as consideration for a transaction authorized by this section upon such terms as the Secretary considers appropriate to promote the purpose of this section.

(2) The term of a lease under paragraph (1) may not exceed 10 years, unless the Secretary of Defense approves a term in excess of 10 years for purposes of this section.

(3) A lease under this subsection may provide that, upon termination of the lease term, the United States shall have the right of first refusal to acquire the facility covered by the lease.

(e) Requirement for Competition.—The Secretary of the Navy shall use competitive procedures for purposes of selecting the recipient of real or personal property under subsection (b) and the lessee of real or personal property under subsection (c).

(f) Consideration.—(1) As consideration for the conveyance of real or personal property under subsection (b), or for the lease of real or personal property under subsection (c), the Secretary of the Navy shall accept cash, real property, personal property, or services, or any combination thereof, in an aggregate amount equal to not less than the fair market value of the real or personal property conveyed or leased.

(2) Subject to subsection (i), the services accepted by the Secretary under paragraph (1) may include the following:

(A) The construction or improvement of facilities at Ford Island.

(B) The restoration or rehabilitation of real property at Ford Island.

(C) The provision of property support services for property or facilities at Ford Island.


(g) Notice and Wait Requirements.—The Secretary of the Navy may carry out a transaction authorized by this section only after the end of the 20-day period beginning on the date on which the Secretary submits, in an electronic medium pursuant to section 480 of this title, to the appropriate committees of Congress notice of the transaction, including a detailed description of the transaction and a justification for the transaction specifying the manner in which the transaction will meet the purposes of this section.

(h) Ford Island Improvement Account.—(1) There is established on the books of the Treasury an account to be known as the "Ford Island Improvement Account".

(2) There shall be deposited into the account the following amounts:

(A) Amounts authorized and appropriated to the account.

(B) Except as provided in subsection (c)(4)(B), the amount of any cash payment received by the Secretary for a transaction under this section.


(i) Use of Account.—(1) Subject to paragraph (2), to the extent provided in advance in appropriations Acts, funds in the Ford Island Improvement Account may be used as follows:

(A) To carry out or facilitate the carrying out of a transaction authorized by this section.

(B) To carry out improvements of property or facilities at Ford Island.

(C) To obtain property support services for property or facilities at Ford Island.


(2) To extent that the authorities provided under subchapter IV of this chapter are available to the Secretary of the Navy, the Secretary may not use the authorities in this section to acquire, construct, or improve family housing units, military unaccompanied housing units, or ancillary supporting facilities related to military housing.

(3)(A) The Secretary may transfer funds from the Ford Island Improvement Account to the following funds:

(i) The Department of Defense Family Housing Improvement Fund established by section 2883(a)(1) of this title.

(ii) The Department of Defense Military Unaccompanied Housing Improvement Fund established by section 2883(a)(2) of this title.


(B) Amounts transferred under subparagraph (A) to a fund referred to in that subparagraph shall be available in accordance with the provisions of section 2883 of this title for activities authorized under subchapter IV of this chapter at Ford Island.

(j) Inapplicability of Certain Property Management Laws.—Except as otherwise provided in this section, transactions under this section shall not be subject to the following:

(1) Sections 2667 and 2696 of this title.

(2) Section 501 of the McKinney-Vento Homeless Assistance Act (42 U.S.C. 11411).

(3) Subchapter II of chapter 5 and sections 541–555 of title 40.


(k) Scoring.—Nothing in this section shall be construed to waive the applicability to any lease entered into under this section of the budget scorekeeping guidelines used to measure compliance with the Balanced Budget and Emergency Deficit Control Act of 1985.

(l) Property Support Service Defined.—In this section, the term "property support service" means the following:

(1) Any utility service or other service listed in section 2686(a) of this title.

(2) Any other service determined by the Secretary to be a service that supports the operation and maintenance of real property, personal property, or facilities.

(Added Pub. L. 106–65, div. B, title XXVIII, §2802(a)(1), Oct. 5, 1999, 113 Stat. 845; amended Pub. L. 106–398, §1 [[div. A], title X, §1087(a)(16)], Oct. 30, 2000, 114 Stat. 1654, 1654A-291; Pub. L. 107–107, div. A, title X, §1048(d)(1), Dec. 28, 2001, 115 Stat. 1227; Pub. L. 107–217, §3(b)(18), Aug. 21, 2002, 116 Stat. 1296; Pub. L. 111–383, div. B, title XXVIII, §2803(c), Jan. 7, 2011, 124 Stat. 4459; Pub. L. 115–91, div. B, title XXVIII, §2801(a)(11), Dec. 12, 2017, 131 Stat. 1842.)


Editorial Notes

References in Text

The Balanced Budget and Emergency Deficit Control Act of 1985, referred to in subsec. (k), is title II of Pub. L. 99–177, Dec. 12, 1985, 99 Stat. 1038, as amended, which enacted chapter 20 (§900 et seq.) and sections 654 to 656 of Title 2, The Congress, amended sections 602, 622, 631 to 642, and 651 to 653 of Title 2, sections 1104 to 1106, and 1109 of Title 31, Money and Finance, and section 911 of Title 42, The Public Health and Welfare, repealed section 661 of Title 2, enacted provisions set out as notes under section 900 of Title 2 and section 911 of Title 42, and amended provisions set out as a note under section 621 of Title 2. For complete classification of this Act to the Code, see Short Title note set out under section 900 of Title 2 and Tables.

Amendments

2017—Subsec. (g). Pub. L. 115–91 added subsec. (g) and struck out former subsec. (g) which set out notice and wait requirements for a transaction authorized by this section.

2011—Subsec. (g)(2). Pub. L. 111–383 inserted before period at end "or, if earlier, a period of 20 days has elapsed from the date on which a copy of the notification is provided in an electronic medium pursuant to section 480 of this title".

2002—Subsec. (j)(3). Pub. L. 107–217 substituted "Subchapter II of chapter 5 and sections 541–555 of title 40" for "Sections 202 and 203 of the Federal Property and Administrative Services Act of 1949 (40 U.S.C. 483, 484)".

2001—Subsec. (j)(2). Pub. L. 107–107 substituted "McKinney-Vento Homeless Assistance Act" for "Stewart B. McKinney Homeless Assistance Act".

2000—Subsec. (k). Pub. L. 106–398 inserted "and" after "Balanced Budget".

§2815. Military installation resilience projects

(a) Projects Required.—The Secretary of Defense shall carry out military construction projects for military installation resilience, in accordance with section 2802 of this title (except as provided in subsections (d)(3) and (e)).

(b) Congressional Notification.—(1) When a decision is made to carry out a project under this section, the Secretary of Defense shall notify the congressional defense committees of that decision.

(2) The Secretary of Defense shall include in each notification submitted under paragraph (1) the rationale for how the project would—

(A) enhance military installation resilience;

(B) enhance mission assurance;

(C) support mission critical functions; and

(D) address known vulnerabilities.


(c) Timing of Projects.—Except as provided in subsection (e)(2), a project may be carried out under this section only after the end of the 14-day period beginning on the date that notification with respect to that project under subsection (b) is received by the congressional defense committees in an electronic medium pursuant to section 480 of this title.

(d) Location of Projects.—Projects carried out pursuant to this section may be carried out—

(1) on a military installation;

(2) on a facility used by the Department of Defense that is owned and operated by a State, the District of Columbia, the Commonwealth of Puerto Rico, American Samoa, Guam, the Commonwealth of the Northern Mariana Islands, or the Virgin Islands, even if the facility is not under the jurisdiction of the Department of Defense, if the Secretary of Defense determines that the facility is subject to significant use by the armed forces for testing or training; or

(3) outside of a military installation or facility described in paragraph (2) if the Secretary concerned determines that the project would preserve or enhance the resilience of—

(A) a military installation;

(B) a facility described in paragraph (2); or

(C) community infrastructure determined by the Secretary concerned to be necessary to maintain, improve, or rapidly reestablish installation mission assurance and mission-essential functions.


(e) Alternative Funding Source.—(1) In carrying out a project under this section, the Secretary concerned may use amounts available for operation and maintenance for the military department concerned if the Secretary concerned submits a notification to the congressional defense committees of the decision to carry out the project using such amounts and includes in the notification—

(A) the current estimate of the cost of the project;

(B) the source of funds for the project; and

(C) a certification that deferral of the project for inclusion in the next Military Construction Authorization Act would be inconsistent with national security or the protection of health, safety, or environmental quality, as the case may be.


(2) A project carried out under this section using amounts under paragraph (1) may be carried out only after the end of the 7-day period beginning on the date on which a copy of the notification described in paragraph (1) is provided in an electronic medium pursuant to section 480 of this title.

(3) The maximum aggregate amount that the Secretary concerned may obligate from amounts available to the military department concerned for operation and maintenance in any fiscal year for projects under the authority of this subsection is $125,000,000.

(f) Annual Report.—Not later than 90 days after the end of each fiscal year until December 31, 2025, the Secretary of Defense shall submit to the congressional defense committees a report on the status of the planned and active projects carried out under this section (including completed projects), and shall include in the report with respect to each such project the following information:

(1) The title, location, a brief description of the scope of work, the original project cost estimate, and the current working cost estimate.

(2) The information provided under subsection (b)(2).

(3) Such other information as the Secretary considers appropriate.

(Added Pub. L. 116–92, div. B, title XXVIII, §2801(b)(1), Dec. 20, 2019, 133 Stat. 1880; amended Pub. L. 116–283, div. A, title III, §315(a), Jan. 1, 2021, 134 Stat. 3514; Pub. L. 118–31, div. B, title XXVIII, §2804, Dec. 22, 2023, 137 Stat. 744.)


Editorial Notes

Prior Provisions

A prior section 2815, added Pub. L. 106–398, §1 [div. B, title XXVIII, §2801(b)(1)], Oct. 30, 2000, 114 Stat. 1654, 1654A-412; amended Pub. L. 107–314, div. A, title X, §1062(a)(14), Dec. 2, 2002, 116 Stat. 2650, related to annual evaluation of joint use military construction projects, prior to repeal by Pub. L. 112–81, div. A, title X, §1061(23)(A), Dec. 31, 2011, 125 Stat. 1584.

Amendments

2023—Subsec. (e)(3). Pub. L. 118–31 substituted "$125,000,000" for "$100,000,000".

2021—Subsec. (a). Pub. L. 116–283, §315(a)(1), inserted "(except as provided in subsections (d)(3) and (e))" before period at end.

Subsec. (c). Pub. L. 116–283, §315(a)(2), substituted "Except as provided in subsection (e)(2), a project" for "A project".

Subsecs. (d) to (f). Pub. L. 116–283, §315(a)(3), (4), added subsecs. (d) and (e) and redesignated former subsec. (d) as (f).

§2815a. Stormwater management projects for installation and defense access road resilience and waterway and ecosystems conservation

(a) Projects Authorized.—The Secretary concerned may carry out a stormwater management project on or related to a military installation for the purpose of—

(1) improving military installation resilience or the resilience of a defense access road or other essential civilian infrastructure supporting the military installation; and

(2) protecting nearby waterways and stormwater-stressed ecosystems.


(b) Project Methods and Funding Sources.—Using such amounts as may be provided in advance in appropriation Acts, the Secretary concerned may carry out a stormwater management project under this section as, or as part of, any of the following:

(1) An authorized military construction project.

(2) An unspecified minor military construction project under section 2805 of this title, including using appropriations available for operation and maintenance subject to the limitation in subsection (c) of such section.

(3) A military installation resilience project under section 2815 of this title, including the use of appropriations available for operations and maintenance subject to the limitation of subsection (e)(3) of such section.

(4) A defense community infrastructure resilience project under section 2391(d) of this title.

(5) A construction project under section 2914 of this title.

(6) A reserve component facility project under section 18233 of this title.

(7) A defense access road project under section 210 of title 23.


(c) Project Priorities.—In selecting stormwater management projects to be carried out under this section, the Secretary concerned shall give a priority to project proposals involving the retrofitting of buildings and grounds on a military installation or retrofitting a defense access road to reduce stormwater runoff and ponding or standing water that includes the combination of stormwater runoff and water levels resulting from extreme weather conditions.

(d) Project Activities.—Activities carried out as part of a stormwater management project under this section may include, but are not limited to, the following:

(1) The installation, expansion, or refurbishment of stormwater ponds and other water-slowing and retention measures.

(2) The installation of permeable pavement in lieu of, or to replace existing, nonpermeable pavement.

(3) The use of planters, tree boxes, cisterns, and rain gardens to reduce stormwater runoff.


(e) Project Coordination.—In the case of a stormwater management project carried out under this section on or related to a military installation and any project related to the same installation carried out under section 2391(d), 2815, or 2914 of this title, the Secretary concerned shall ensure coordination between the projects regarding the water access, management, conservation, security, and resilience aspects of the projects.

(f) Annual Report.—(1) Not later than 90 days after the end of each fiscal year, each Secretary concerned shall submit to the congressional defense committees a report describing—

(A) the status of planned and active stormwater management projects carried out by that Secretary under this section; and

(B) all projects completed by the Secretary concerned during the previous fiscal year.


(2) Each report shall include the following information with respect to each stormwater management project described in the report:

(A) The title, location, a brief description of the scope of work, the original project cost estimate, and the current working cost estimate.

(B) The rationale for how the project will—

(i) improve military installation resilience or the resilience of a defense access road or other essential civilian infrastructure supporting a military installation; and

(ii) protect waterways and stormwater-stressed ecosystems.


(C) Such other information as the Secretary concerned considers appropriate.


(g) Definitions.—In this section:

(1) The term "defense access road" means a road certified to the Secretary of Transportation as important to the national defense under the provisions of section 210 of title 23.

(2) The terms "facility" and "State" have the meanings given those terms in section 18232 of this title.

(3) The term "military installation" includes a facility of a reserve component owned by a State rather than the United States.

(4) The term "military installation resilience" has the meaning given that term in section 101(e)(8) 1 of this title.

(5) The term "Secretary concerned" means—

(A) the Secretary of a military department with respect to military installations under the jurisdiction of that Secretary; and

(B) the Secretary of Defense with respect to matters concerning the Defense Agencies and facilities of a reserve component owned by a State rather than the United States.

(Added Pub. L. 117–81, div. B, title XXVIII, §2803, Dec. 27, 2021, 135 Stat. 2186.)


Editorial Notes

References in Text

Section 101(e)(8) of this title, referred to in subsec. (g)(4), was redesignated section 101(f)(8) of this title, and a new subsec. (e) of section 101 was added, by Pub. L. 118–31, div. A, title XVII, §1713(a), Dec. 22, 2023, 137 Stat. 625.

1 See References in Text note below.

§2816. Consideration of energy security and energy resilience in life-cycle cost for military construction

(a) In General.—(1) The Secretary concerned, when evaluating the life-cycle designed cost of a covered military construction project, shall include as a facility requirement the long-term consideration of energy security and energy resilience that would ensure that the resulting facility is capable of continuing to perform its missions, during the life of the facility, in the event of a natural or human-caused disaster, an attack, or any other unplanned event that would otherwise interfere with the ability of the facility to perform its missions.

(2) A facility requirement under paragraph (1) shall not be weighed, for cost purposes, against other facility requirements in determining the design of the facility.

(b) Inclusion in the Building Life-cycle Cost Program.—The Secretary shall include the requirements of subsection (a) in applying the latest version of the building life-cycle cost program, as developed by the National Institute of Standards and Technology, to consider on-site distributed energy assets in a building design for a covered military construction project.

(c) Covered Military Construction Project Defined.—(1) In this section, the term "covered military construction project" means a military construction project for a facility that is used to perform critical functions during a natural or human-caused disaster, an attack, or any other unplanned event.

(2) For purposes of paragraph (1), the term "facility" includes at a minimum any of the following:

(A) Operations centers.

(B) Nuclear command and control facilities.

(C) Integrated strategic and tactical warning and attack assessment facilities.

(D) Continuity of government facilities.

(E) Missile defense facilities.

(F) Air defense facilities.

(G) Hospitals.

(H) Armories and readiness centers of the National Guard.

(I) Communications facilities.

(J) Satellite and missile launch and control facilities.

(Added Pub. L. 116–283, div. B, title XXVIII, §2804(a), Jan. 1, 2021, 134 Stat. 4320.)

§2817. Authority for certain construction projects in friendly foreign countries

(a) Construction Authorized.—Using funds available for operations and maintenance, the Secretary of Defense may carry out a construction project in a friendly foreign country, and perform planning and design to support such a project, that the Secretary determines meets each of the following conditions:

(1) The commander of the geographic combatant command in which the construction project will be carried out identified the construction project as necessary to support vital United States military requirements at an air port of debarkation, sea port of debarkation, or rail or other logistics support location.

(2) The construction project will not be carried out at a military installation.

(3) The funds made available under the authority of this section for the construction project—

(A) will be sufficient to—

(i) construct a complete and usable facility or make an improvement to a facility; or

(ii) complete the repair of an existing facility or improvement to a facility; and


(B) will not require additional funds from other Department of Defense accounts.


(4) The level of construction for the construction project may not exceed the minimum necessary to meet the military requirements identified under paragraph (1).

(5) Deferral of the construction project pending inclusion of the construction project proposal in the national defense authorization Act for a subsequent fiscal year is inconsistent with the military requirements identified under paragraph (1) and other national security or national interests of the United States.


(b) Congressional Notification.—

(1) Notification required.—Upon determining to carry out a construction project under this section that has an estimated cost in excess of the amounts authorized for unspecified minor military construction projects under section 2805(c) of this title, the Secretary of Defense shall submit to the specified congressional committees a notification of such determination.

(2) Elements.—The notification required by paragraph (1) shall include the following:

(A) A certification that the conditions specified in subsection (a) are satisfied with regard to the construction project.

(B) A justification for such project.

(C) An estimate of the cost of such project.


(3) Notice and wait.—The Secretary of Defense may carry out a construction project only after the end of the 30-day period beginning on the date the notice required by paragraph (1) is received by the specified congressional committees in an electronic medium pursuant to section 480 of this title.


(c) Annual Limitations on Use of Authority.—

(1) Total cost limitation.—The Secretary of Defense may not obligate more than $200,000,000 in any fiscal year under the authority provided by this section.

(2) Additional obligation authority.—Notwithstanding paragraph (1), the Secretary of Defense may authorize the obligation under this section of not more than an additional $10,000,000 from funds available for operations and maintenance for a fiscal year if the Secretary determines that the additional funds are needed for costs associated with contract closeouts for all construction projects during such fiscal year.

(3) Project limitation.—The maximum amount that the Secretary may obligate for a single construction project is $15,000,000.


(d) Specified Congressional Committees Defined.—In this section, the term "specified congressional committees" means—

(1) the Committee on Armed Services and the Subcommittee on Defense and the Subcommittee on Military Construction, Veterans Affairs, and Related Agencies of the Committee on Appropriations of the Senate; and

(2) the Committee on Armed Services and the Subcommittee on Defense and the Subcommittee on Military Construction, Veterans Affairs, and Related Agencies of the Committee on Appropriations of the House of Representatives.

(Added Pub. L. 118–31, div. B, title XXVIII, §2805, Dec. 22, 2023, 137 Stat. 744.)