25 USC 5902: Mortgage review and processing
Result 1 of 1
   
 
25 USC 5902: Mortgage review and processing Text contains those laws in effect on May 21, 2026
From Title 25-INDIANSCHAPTER 51-TRIBAL TRUST LAND HOMEOWNERSHIP
Jump To: Source Credit

§5902. Mortgage review and processing

(a) Review and processing deadlines

(1) In general

As soon as practicable after receiving a proposed residential leasehold mortgage, business leasehold mortgage, land mortgage, or right-of-way document, the applicable Bureau office shall notify the lender that the proposed residential leasehold mortgage, business leasehold mortgage, or right-of-way document has been received.

(2) Preliminary review

(A) In general

Not later than 10 calendar days after receipt of a proposed residential leasehold mortgage, business leasehold mortgage, land mortgage, or right-of-way document, the applicable Bureau office shall conduct and complete a preliminary review of the residential leasehold mortgage, business leasehold mortgage, land mortgage, or right-of-way document to verify that all required documents are included.

(B) Incomplete documents

As soon as practicable, but not more than 2 calendar days, after finding that any required documents are missing under subparagraph (A), the applicable Bureau office shall notify the lender of the missing documents.

(3) Approval or disapproval

(A) Leasehold mortgages

Not later than 20 calendar days after receipt of a complete executed residential leasehold mortgage or business leasehold mortgage, proof of required consents, and other required documentation, the applicable Bureau office shall approve or disapprove the residential leasehold mortgage or business leasehold mortgage.

(B) Right-of-way documents

Not later than 30 calendar days after receipt of a complete executed right-of-way document, proof of required consents, and other required documentation, the applicable Bureau office shall approve or disapprove the right-of-way document.

(C) Land mortgages

Not later than 30 calendar days after receipt of a complete executed land mortgage, proof of required consents, and other required documentation, the applicable Bureau office shall approve or disapprove the land mortgage.

(D) Requirements

The determination of whether to approve or disapprove a residential leasehold mortgage or business leasehold mortgage under subparagraph (A), a right-of-way document under subparagraph (B), or a land mortgage under subparagraph (C)-

(i) shall be in writing; and

(ii) in the case of a determination to disapprove a residential leasehold mortgage, business leasehold mortgage, right-of-way document, or land mortgage shall, state the basis for the determination.

(E) Application

This paragraph shall not apply to a residential leasehold mortgage or business leasehold mortgage with respect to Indian land in cases in which the applicant for the residential leasehold mortgage or business leasehold mortgage is an Indian tribe (as defined in subsection (d) of section 415 of this title) that has been approved for leasing under subsection (h) of that section.

(4) Certified title status reports

(A) Completion of reports

(i) In general

Not later than 10 calendar days after the applicable Bureau office approves a residential leasehold mortgage, business leasehold mortgage, land mortgage, or right-of-way document under paragraph (3), the applicable Bureau office shall complete the processing of, as applicable-

(I) a first certified title status report, if a first certified title status report was not completed prior to the approval of the residential leasehold mortgage, business leasehold mortgage, land mortgage, or right-of-way document; and

(II) a subsequent certified title status report.

(ii) Requests for first certified title status reports

Notwithstanding clause (i), not later than 14 calendar days after the applicable Bureau office receives a request for a first certified title status report from an applicant for a residential leasehold mortgage, business leasehold mortgage, land mortgage, or right-of-way document under paragraph (1), the applicable Bureau office shall complete the processing of the first certified title status report.

(B) Notice

(i) In general

As soon as practicable after completion of the processing of, as applicable, a first certified title status report or a subsequent certified title status report under subparagraph (A), but by not later than the applicable deadline described in that subparagraph, the applicable Bureau office shall give notice of the completion to the lender.

(ii) Form of notice

The applicable Bureau office shall give notice under clause (i)-

(I) electronically through secure, encryption software; and

(II) through the United States mail.

(iii) Option to opt out

The lender may opt out of receiving notice electronically under clause (ii)(I).

(b) Notices

(1) In general

If the applicable Bureau office does not complete the review and processing of mortgage packages under subsection (a) (including any corresponding first certified title status report or subsequent certified title status report under paragraph (4) of that subsection) by the applicable deadline described in that subsection, immediately after missing the deadline, the applicable Bureau office shall provide notice of the delay in review and processing to-

(A) the party that submitted the mortgage package or requested the first certified title status report; and

(B) the lender for which the mortgage package (including any corresponding first certified title status report or subsequent certified title status report) is being requested.

(2) Requests for updates

In addition to providing the notices required under paragraph (1), not later than 2 calendar days after receiving a relevant inquiry with respect to a submitted mortgage package from the party that submitted the mortgage package or the lender for which the mortgage package (including any corresponding first certified title status report or subsequent certified title status report) is being requested or an inquiry with respect to a requested first certified title status report from the party that requested the first certified title status report, the applicable Bureau office shall respond to the inquiry.

(c) Delivery of first and subsequent certified title status reports

Notwithstanding any other provision of law, any first certified title status report and any subsequent certified title status report, as applicable, shall be delivered directly to-

(1) the lender;

(2) any local or regional agency office of the Bureau that requests the first certified title status report or subsequent certified title status report;

(3) in the case of a proposed residential leasehold mortgage or land mortgage, the relevant Federal agency that insures or guarantees the loan; and

(4) if requested, any individual or entity described in section 150.303 of title 25, Code of Federal Regulations (as in effect on May 4, 2026).

(d) Access to Trust Asset and Accounting Management System (TAAMS)

Beginning on May 4, 2026, the relevant Federal agencies and Indian Tribes shall have read-only access to portals containing the relevant land documents from the Trust Asset and Accounting Management System (commonly known as "TAAMS") maintained by the Bureau.

(e) Annual report

(1) In general

Not later than March 1 of each calendar year, the Director shall submit to the Committee on Indian Affairs of the Senate and the Committee on Natural Resources of the House of Representatives a report describing-

(A) for the most recent calendar year, the number of requests received to complete residential leasehold mortgage packages, business leasehold mortgage packages, land mortgage packages, and right-of-way document packages (including any requests for corresponding first certified title status reports and subsequent certified title status reports), including a detailed description of-

(i) requests that were and were not successfully completed by the applicable deadline described in subsection (a) by each applicable Bureau office; and

(ii) the reasons for each applicable Bureau office not meeting any applicable deadlines; and


(B) the length of time needed by each applicable Bureau office during the most recent calendar year to provide the notices required under subsection (b)(1).

(2) Requirement

In submitting the report required under paragraph (1), the Director shall maintain the confidentiality of personally identifiable information of the parties involved in requesting the completion of residential leasehold mortgage packages, business leasehold mortgage packages, land mortgage packages, and right-of-way document packages (including any corresponding first certified title status reports and subsequent certified title status reports).

(f) GAO study

Not later than 1 year after May 4, 2026, the Comptroller General of the United States shall submit to the Committee on Indian Affairs of the Senate and the Committee on Natural Resources of the House of Representatives a report that includes-

(1) an evaluation of the need for residential leasehold mortgage packages, business leasehold mortgage packages, land mortgage packages, and right-of-way document packages of each Indian Tribe to be digitized for the purpose of streamlining and expediting the completion of mortgage packages for residential mortgages on Indian land (including the corresponding first certified title status reports and subsequent certified title status reports); and

(2) an estimate of the time and total cost necessary for Indian Tribes to digitize the records described in paragraph (1), in conjunction with assistance in that digitization from the Bureau.

( Pub. L. 119–88, §3, May 4, 2026, 140 Stat. 813 .)