10 USC Subtitle A, PART IV, CHAPTER 144B, SUBCHAPTER III: COST, SCHEDULE, AND PERFORMANCE OF MAJOR DEFENSE ACQUISITION PROGRAMS
From Title 10—ARMED FORCESSubtitle A—General Military LawPART IV—SERVICE, SUPPLY, AND PROCUREMENTCHAPTER 144B—WEAPON SYSTEMS DEVELOPMENT AND RELATED MATTERS

SUBCHAPTER III—COST, SCHEDULE, AND PERFORMANCE OF MAJOR DEFENSE ACQUISITION PROGRAMS

Sec.
2448a.
Program cost, fielding, and performance goals in planning major defense acquisition programs.
2448b.
Independent technical risk assessments.

        

Repeal of Subchapter

Pub. L. 116–283, div. A, title XVIII, §§1801(d), 1851(d)(1), Jan. 1, 2021, 134 Stat. 4151, 4273, provided that, effective Jan. 1, 2022, with additional provisions for delayed implementation and applicability of existing law, chapter 144B of this title, and therefore this subchapter, is repealed. See Effective Date of Repeal note below.

Effective Date of Repeal

Repeal effective Jan. 1, 2022, with additional provisions for delayed implementation and applicability of existing law, see section 1801(d) of Pub. L. 116–283, set out as an Effective Date of 2021 Amendment note preceding section 3001 of this title.

§2448a. Program cost, fielding, and performance goals in planning major defense acquisition programs

(a) Program Cost and Fielding Targets.—(1) Before funds are obligated for technology development, systems development, or production of a major defense acquisition program, the designated milestone decision authority for the program shall ensure, by establishing the goals described in paragraph (2), that the program will—

(A) be affordable;

(B) incorporate program planning that anticipates the evolution of capabilities to meet changing threats, technology insertion, and interoperability; and

(C) be fielded when needed.


(2) The goals described in this paragraph are goals for—

(A) the procurement unit cost and sustainment cost (referred to in this section as the "program cost targets");

(B) the date for initial operational capability (referred to in this section as the "fielding target"); and

(C) technology maturation, prototyping, and a modular open system approach to evolve system capabilities and improve interoperability.


(b) Definitions.—In this section:

(1) The term "procurement unit cost" has the meaning provided in section 2432(a)(2) of this title.

(2) The term "initial capabilities document" has the meaning provided in section 2366a(d)(2) of this title.

(Added Pub. L. 114–328, div. A, title VIII, §807(a)(1), Dec. 23, 2016, 130 Stat. 2260; amended Pub. L. 115–232, div. A, title VIII, §831(a), Aug. 13, 2018, 132 Stat. 1857.)

Transfer of Section

Pub. L. 116–283, div. A, title XVIII, §§1801(d), 1847(e)(1), Jan. 1, 2021, 134 Stat. 4151, 4256, provided that, effective Jan. 1, 2022, with additional provisions for delayed implementation and applicability of existing law, this section is transferred to chapter 322 of this title, inserted after the table of sections at the beginning of subchapter IV, and redesignated as section 4271 of this title. See Effective Date of 2021 Amendment note below.

Amendments

2018—Subsec. (a)(1). Pub. L. 115–232, §831(a)(1), (2), in introductory provisions, substituted "designated milestone decision authority for the program shall ensure, by establishing the goals described in paragraph (2), that the program" for "Secretary of Defense shall ensure, by establishing the goals described in paragraph (2), that the milestone decision authority for the major defense acquisition program approves a program that".

Subsecs. (b), (c). Pub. L. 115–232, §831(a)(3), (4), redesignated subsec. (c) as (b) and struck out former subsec. (b). Prior to amendment, text of subsec. (b) read as follows: "The responsibilities of the Secretary of Defense in subsection (a) may be delegated only to the Deputy Secretary of Defense."

Effective Date of 2021 Amendment

Amendment by Pub. L. 116–283 effective Jan. 1, 2022, with additional provisions for delayed implementation and applicability of existing law, see section 1801(d) of Pub. L. 116–283, set out as a note preceding section 3001 of this title.

Effective Date

Pub. L. 114–328, div. A, title VIII, §807(a)(2), Dec. 23, 2016, 130 Stat. 2261, provided that: "Subchapter III of chapter 144B of title 10, United States Code, as added by paragraph (1), shall apply with respect to major defense acquisition programs that reach Milestone A after October 1, 2017."

Program Cost and Field Targets

Pub. L. 114–328, div. A, title IX, §925(b), Dec. 23, 2016, 130 Stat. 2361, as amended by Pub. L. 115–232, div. A, title VIII, §831(b)(4), Aug. 13, 2018, 132 Stat. 1857, provided that: "The Secretary of Defense shall establish a process to develop program cost and fielding targets pursuant to section 2448a of title 10, United States Code, that—

"(1) is co-chaired by the designated milestone decision authority for the major defense acquisition program and the Vice Chief of Staff of the armed force concerned or, in the case of a program for which an alternate milestone decision authority is designated under section 2430(d)(2) of such title, the Vice Chairman of the Joint Chiefs of Staff;

"(2) is supported by—

"(A) the Joint Staff, to provide expertise on joint military capabilities, capability gaps, and performance requirements;

"(B) the Office of Cost Assessment and Program Evaluation, to provide expertise in resource allocation, operations research, systems analysis, and cost estimation; and

"(C) other Department of Defense organizations determined appropriate by the Secretary; and

"(3) ensures that appropriate trade-offs are made among life-cycle cost, schedule, and performance objectives and procurement quantity objectives."

§2448b. Independent technical risk assessments

(a) In General.—With respect to a major defense acquisition program, the Secretary of Defense shall conduct or approve independent technical risk assessments—

(1) before any decision to grant Milestone A approval for the program pursuant to section 2366a of this title, that identifies critical technologies and manufacturing processes that need to be matured; and

(2) before any decision to grant Milestone B approval for the program pursuant to section 2366b of this title, any decision to enter into low-rate initial production or full-rate production, or at any other time considered appropriate by the Secretary, that includes the identification of any critical technologies or manufacturing processes that have not been successfully demonstrated in a relevant environment.


(b) Guidance.—The Secretary shall issue guidance and a framework for the conduct, execution, and approval of independent technical risk assessments.

(Added Pub. L. 114–328, div. A, title VIII, §807(a)(1), Dec. 23, 2016, 130 Stat. 2261; amended Pub. L. 116–92, div. A, title IX, §902(73), Dec. 20, 2019, 133 Stat. 1552.)

Transfer of Section

Pub. L. 116–283, div. A, title XVIII, §§1801(d), 1847(e)(2), Jan. 1, 2021, 134 Stat. 4151, 4256, provided that, effective Jan. 1, 2022, with additional provisions for delayed implementation and applicability of existing law, this section is transferred to chapter 322 of this title, inserted after section 4271 of this title, and redesignated as section 4272 of this title. See Effective Date of 2021 Amendment note below.

Amendments

2019Pub. L. 116–92 added subsecs. (a) and (b) and struck out former subsecs. (a) and (b) which read as follows:

"(a) In General.—With respect to a major defense acquisition program, the Secretary of Defense shall ensure that an independent technical risk assessment is conducted—

"(1) before any decision to grant Milestone A approval for the program pursuant to section 2366a of this title, that identifies critical technologies and manufacturing processes that need to be matured; and

"(2) before any decision to grant Milestone B approval for the program pursuant to section 2366b of this title, any decision to enter into low-rate initial production or full-rate production, or at any other time considered appropriate by the Secretary, that includes the identification of any critical technologies or manufacturing processes that have not been successfully demonstrated in a relevant environment.

"(b) Categorization of Technical Risk Levels.—The Secretary shall issue guidance and a framework for categorizing the degree of technical and manufacturing risk in a major defense acquisition program."

Effective Date of 2021 Amendment

Amendment by Pub. L. 116–283 effective Jan. 1, 2022, with additional provisions for delayed implementation and applicability of existing law, see section 1801(d) of Pub. L. 116–283, set out as a note preceding section 3001 of this title.

Effective Date

Section applicable with respect to major defense acquisition programs that reach Milestone A after Oct. 1, 2017, see section 807(a)(2) of Pub. L. 114–328, set out as a note under section 2448a of this title.