10 USC 2410m: Retention of amounts collected from contractor during the pendency of contract dispute
Result 1 of 1
   
 
10 USC 2410m: Retention of amounts collected from contractor during the pendency of contract dispute Text contains those laws in effect on January 2, 2001
From Title 10-ARMED FORCESSubtitle A-General Military LawPART IV-SERVICE, SUPPLY, AND PROCUREMENTCHAPTER 141-MISCELLANEOUS PROCUREMENT PROVISIONS

§2410m. Retention of amounts collected from contractor during the pendency of contract dispute

(a) Retention of Funds.-Notwithstanding sections 1552(a) and 3302(b) of title 31, any amount, including interest, collected from a contractor as a result of a claim made by a military department or Defense Agency under the Contract Disputes Act of 1978 (41 U.S.C. 601 et seq.), shall remain available in accordance with this section to pay-

(1) any settlement of the claim by the parties;

(2) any judgment rendered in the contractor's favor on an appeal of the decision on that claim to the Armed Services Board of Contract Appeals under section 7 of such Act (41 U.S.C. 606); or

(3) any judgment rendered in the contractor's favor in an action on that claim in a court of the United States.


(b) Period of Availability.-(1) The period of availability of an amount under subsection (a), in connection with a claim-

(A) expires 180 days after the expiration of the period for bringing an action on that claim in the United States Court of Federal Claims under section 10(a) of the Contract Disputes Act of 1978 (41 U.S.C. 609(a)) if, within that 180-day period-

(i) no appeal on the claim is commenced at the Armed Services Board of Contract Appeals under section 7 of such Act; and

(ii) no action on the claim is commenced in a court of the United States; or


(B) if not expiring under subparagraph (A), expires-

(i) in the case of a settlement of the claim, 180 days after the date of the settlement; or

(ii) in the case of a judgment rendered on the claim in an appeal to the Armed Services Board of Contract Appeals under section 7 of the Contract Disputes Act of 1978 or an action in a court of the United States, 180 days after the date on which the judgment becomes final and not appealable.


(2) While available under this section, an amount may be obligated or expended only for a purpose described in subsection (a).

(3) Upon the expiration of the period of availability of an amount under paragraph (1), the amount shall be covered into the Treasury as miscellaneous receipts.

(c) Reporting Requirement.-Each year, the Under Secretary of Defense (Comptroller) shall submit to Congress a report on the amounts, if any, that are available for obligation pursuant to this section. The report shall include, at a minimum, the following:

(1) The total amount available for obligation.

(2) The total amount collected from contractors during the year preceding the year in which the report is submitted.

(3) The total amount disbursed in such preceding year and a description of the purpose for each disbursement.

(4) The total amount returned to the Treasury in such preceding year.

(Added Pub. L. 105–85, div. A, title VIII, §831(a), Nov. 18, 1997, 111 Stat. 1841 .)

References in Text

The Contract Disputes Act of 1978, referred to in subsec. (a), is Pub. L. 95–563, Nov. 1, 1978, 92 Stat. 2383 , as amended, which is classified principally to chapter 9 (§601 et seq.) of Title 41, Public Contracts. For complete classification of this Act to the Code see Short Title note set out under section 601 of Title 41 and Tables.