§2433a. Critical cost growth in major defense acquisition programs
(a)
(1) determine the root cause or causes of the critical cost growth in accordance with applicable statutory requirements and Department of Defense policies, procedures, and guidance; and
(2) in consultation with the Director of Cost Assessment and Program Evaluation, carry out an assessment of-
(A) the projected cost of completing the program if current requirements are not modified;
(B) the projected cost of completing the program based on reasonable modification of such requirements;
(C) the rough order of magnitude of the costs of any reasonable alternative system or capability; and
(D) the need to reduce funding for other programs due to the growth in cost of the program.
(b)
(2) A certification described by this paragraph with respect to a major defense acquisition program is a written certification that-
(A) the continuation of the program is essential to the national security;
(B) there are no alternatives to the program which will provide acceptable capability to meet the joint military requirement (as defined in section 181(g)(1) of this title) at less cost;
(C) the new estimates of the program acquisition unit cost or procurement unit cost have been determined by the Director of Cost Assessment and Program Evaluation to be reasonable;
(D) the program is a higher priority than programs whose funding must be reduced to accommodate the growth in cost of the program; and
(E) the management structure for the program is adequate to manage and control program acquisition unit cost or procurement unit cost.
(3) A written certification under paragraph (2) shall be accompanied by a report presenting the root cause analysis and assessment carried out pursuant to subsection (a) and the basis for each determination made in accordance with subparagraphs (A) through (E) of paragraph (2), together with supporting documentation.
(c)
(A) restructure the program in a manner that addresses the root cause or causes of the critical cost growth, as identified pursuant to subsection (a), and ensures that the program has an appropriate management structure as set forth in the certification submitted pursuant to subsection (b)(2)(E);
(B) rescind the most recent Milestone approval, or Key Decision Point approval in the case of a space program, for the program and withdraw any associated certification under section 2366a or 2366b of this title;
(C) require a new Milestone approval, or Key Decision Point approval in the case of a space program, for the program before taking any contract action to enter a new contract, exercise an option under an existing contract, or otherwise extend the scope of an existing contract under the program, except to the extent determined necessary by the Milestone Decision Authority, on a non-delegable basis, to ensure that the program can be restructured as intended by the Secretary without unnecessarily wasting resources;
(D) include in the report specified in paragraph (2) a description of all funding changes made as a result of the growth in cost of the program, including reductions made in funding for other programs to accommodate such cost growth; and
(E) conduct regular reviews of the program in accordance with the requirements of section 205 of the Weapon Systems Acquisition Reform Act of 2009.
(2) For purposes of paragraph (1)(D), the report specified in this paragraph is the first Selected Acquisition Report for the program submitted pursuant to section 2432 of this title after the President submits a budget pursuant to section 1105 of title 31, in the calendar year following the year in which the program was restructured.
(d)
(1) an explanation of the reasons for terminating the program;
(2) the alternatives considered to address any problems in the program; and
(3) the course the Department plans to pursue to meet any continuing joint military requirements otherwise intended to be met by the program.
(Added
References in Text
Section 205 of the Weapon Systems Acquisition Reform Act of 2009, referred to in subsec. (c)(1)(E), is section 205 of
Amendments
2011-Subsec. (b)(2)(B).
Reviews of Programs Restructured After Experiencing Critical Cost Growth
[
[For definition of "major defense acquisition program" as used in section 205(c) of